In this guide

Job costs and supplier bills

What each trade was meant to cost, what is spent and owed, what is still to buy, where the job will finish, and the bills that become those costs.

Page: a job's Job Costs page

What it is

Job Costs is one job's money out, trade by trade: what each trade was meant to cost (the budget, one line per estimate section), what is spent (cost entries — supplier and subcontractor bills, labour, stock, plant — plus what is incurred and not billed yet), what is owed (what the issued orders and signed subcontractors still have to bill), what is still to buy (budget nothing has been ordered or spent against, plus the extras named on the line) and the expected final: spent + owed + still to buy. Every figure is ex GST, and every one comes from the same calculation the Money page, the WIP and the reports read, so the numbers agree wherever you see them. The page has tabs for Budget Lines, Cost Entries, Purchase Orders, Subcontractor Claims and Variations; By Cost Type, By Cost Code, Schedule of Values and CVR appear in Accountant mode. It is for the project manager and whoever approves bills.

The page has two views. The plain one, for everyone, shows each trade's Budget, Owed, Spent, Expected final and Over/under. Accountant mode, the switch at the top, adds Still to buy and Var %, the strips, the extra tabs and the tools accounts work with.

At the top, the True value panel answers the one question the page is for in four numbers — Contract, Expected final, Margin at completion and Spent — and under it Needs doing lists what those numbers are waiting on, one action each.

Before you start

  • The Job Costs module must be on (Settings → Team modules).
  • The job needs a budget. With the award automation turned on, Base builds it from the approved estimate when the job is won; otherwise press Create from Estimate on the Budget Lines tab.
  • Cost codes exist. They are seeded for every business; see Cost codes.
  • Approving a bill needs the approve-costs permission; recording one, or adding a cost that's coming, needs the edit-costs permission; closing a month, moving budget or setting a line's still-to-come figure needs the set-forecasts permission. The page tells you when you lack one rather than showing a button that fails.
  • To charge plant and vehicles to the job, turn tracking on for that kind in Settings → Finance → Plant & vehicles and add the items in Settings → Plant & vehicles.

How to

Build the budget from the estimate

  1. On Budget Lines, press Create from Estimate. If the job already has lines, a dialog explains that they will be replaced and that figures you edited by hand are lost; cost entries and purchase orders linked to the old lines move to the new line for the same section or trade, and any with no match are unlinked.
  2. Press Replace N lines to go ahead, or Reconcile instead (set-forecasts permission) to keep every line, bill and order where it is and have Base propose one logged adjustment per difference for you to approve or reject line by line.

Add a line by hand with Add Trade. Analyse with AI asks Base to read the budget against your past jobs. A tab's buttons sit in a row under the tabs, the main one first: Add Trade, Create from Estimate, Analyse with AI and Close month on Budget Lines, Add cost on Cost Entries.

Add a cost that's coming

For a cost you know is on its way and the budget doesn't cover: a switchboard upgrade, an extra day of make-good, a price rise.

  1. On Budget Lines, click the trade to open it.
  2. Under Costs coming that aren't in the budget, press Add a cost that's coming.
  3. Type What it is and the Cost, ex GST.
  4. Choose Who pays:
    • We wear it: press Add it. It shows under the trade's name, and the line's Expected final goes up by its amount.
    • The client pays (once the job is won): press Price the variation. The variation opens priced at cost plus the section's margin, and nothing is added to the forecast. Before the job is won, add it to the estimate instead.

When the cost is in an order or a bill, press Ordered or billed now so it stops counting on top. If it isn't happening, press Not needed and say why. If an order is raised on the line after you added the extra, the line asks whether the extra is in it. Yes, it's in that order closes it; No stops the question.

An extra keeps the description and amount it was added with. To change either, take it off with a reason and add the right one.

Take out scope that's not needed

When part of a won job isn't needed any more, take it out so the budget stops expecting it.

  1. On Budget Lines, click the trade to open it.
  2. Under Outstanding — not yet ordered, point at the line and press Not required at its right (on a phone it sits under the line).
  3. Choose what happens to the money:
    • Keep the saving — no credit to the client. Say why it isn't needed and press Keep the saving. The line's cost comes off the budget and the expected final, and the margin keeps it. The contract sum doesn't change, and the client isn't sent anything.
    • Credit the client — they pay less. Press Raise the credit. A credit variation goes to the client for approval like any other. Once they approve it, the contract sum comes down by the line's price and the budget by its cost.
  4. Either way it's recorded as a variation, so the Variations tab and the trade's budget adjustments show what came out and why. The estimate itself stays as it was won.

The button only shows on a won job, for a line nothing has been ordered against, and if you can raise variations. Before the job is won, delete the line on the estimate instead. If the work is already ordered, reduce the order too, or its committed money keeps the expected final up. A line a pending credit takes out shows credit with the client and its variation number, and isn't offered again.

Tick off the estimate lines that are invoiced

A bill on a trade ticks off the estimate lines it pays for, so Outstanding — not yet ordered shows what is really still to let.

  1. On Budget Lines, click the trade to open it.
  2. Under Outstanding — not yet ordered, a line a bill pays for has a tick, with the supplier, invoice number and amount under it. matched by its description means Base read it off the bill; nobody has confirmed it yet.
  3. If the match is wrong, press Not this line. The line goes back on the list, and Base doesn't match that bill to it again.
  4. If a line is invoiced but has no tick, point at it, press Tick off at its right, pick the bill that pays for it and press Tick off. A bill can pay for several lines; tick each one off against it.

Under each cost entry, pays for names the estimate lines the bill was ticked off against.

A bill ticks off only the part of the line it is: a materials bill ticks the line off under Material, and the labour on the same line stays under Labour until it is done. A subcontractor's bill for a line your crew was priced for ticks off the whole line. Tick off and Not this line need the edit-costs permission. Issue a purchase order and Invite tenders leave out the lines that are ticked off.

Upload the job's invoices

  1. Press Add cost → Upload invoices (under Many at once); the drop opens above the Cost Entries tab. Drop the job's bills — PDFs, scans or photos, as many as you like — or press Choose files. You need the edit-costs permission to see it.
  2. Each file is filed on the job as an Invoice (in the Invoices folder) and read in turn. The list under the drop says what happened to each one as it lands: the supplier, number and ex-GST amount, and the trade it went on.
  3. Base puts the bill on its trade four ways, in this order: the order it pays (a PO number on the invoice, or the supplier's one open order), else the trade it reads from the job's cost sections, else the one trade line that carries its cost code, else where that supplier's earlier bills on this job went. A first-time supplier with no order and no cost code Base can place lands on no trade — put it on one from Cost Entries.
  4. What lands waits for approval: it is on the job and its trade, and it becomes payable only when you tick it on Cost Entries (or the three-way match against its order approves it). Press Review for approval to open the list.
  5. A file that is not an invoice (a quote, a statement) is kept as a document and the list says so; a bill already on the job is told so and never recorded twice.

See the purchase orders on Procurement

Job Costs has no Purchase Orders tab: a job's orders live on its own Purchase Orders page, where each opens onto its scope, what was sent, its bills and its variations. The line under Budget Lines links there, and to Procurement filtered to this job. On Cost Entries, a bill's On PO-… button opens the order it pays. In Accountant mode, what the orders commit, and what is paid and due, is under Committed, accrued, paid and due, beside What's in it.

Open the invoice or purchase order behind a cost

On Cost Entries, each bill carries small links beside its number: Invoice (the filed invoice or an emailed one), Receipt, Xero (a bill pulled from Xero, which Base holds no copy of) and, when it pays an order, Quote, PO and Docket for that order's quote, document and delivery dockets. Open a trade on Budget Lines and the same links sit beside each order and cost entry in its drawer. A Base document opens in the viewer; a Xero link opens Xero.

In the drawer, an order with no PO document filed yet shows Make PO: press it and the purchase order is made from the order and filed on the job, and its PO link appears. An order without its quote shows Quote missing · Attach, and a bill without its invoice Invoice missing · Attach — attach either from there.

Add a bill, receipt, credit note or levy from the paper

On Cost Entries, press Add cost and pick what you have: Bill, Receipt, Credit note or Levy or fee. Each opens a form for that kind of paper.

  1. Give Base the paper any way that suits: drop the PDF or photo on the form, press Choose a file, or on a phone press Take a photo. Base reads the supplier, the number, the date, the total and the GST, and marks each value it read read. Or press Say it and describe it ("Bunnings yesterday, $86.40 on the card, screws and sealant"); Base fills in what you said and marks it heard. Or type it in.
  2. Check every value against the paper shown beside the form. Pick the Order and the Job cost line if Base could not tell.
  3. Press Confirm and save (Save when you typed it all). The form says what was recorded, and Open Job Costs takes you to it.

What each one becomes:

  • A bill lands ex GST with its GST beside it, linked to its order when it names one. A total read off the file waits Awaiting review for someone to approve it; a total you typed counts at once.
  • A receipt is recorded the same way and marked paid on the day of the receipt.
  • A credit note is a negative cost on the bill it credits, on that bill's trade line and order. Name the bill in Invoice it credits, and enter the credit as printed, without a minus sign. A credit read off the file reduces the job's cost once someone approves it, like a bill.
  • A levy or fee (QLeave, a training or safety levy, a permit, a council or infrastructure charge) goes on the job's preliminaries line, GST-free unless the notice shows GST. Fill Paid on if it is already paid; otherwise Due says when.

Saving the same invoice or credit note twice adds nothing: the form says it is already in job costs.

Which trade it lands on. A bill on an order goes on that order's trade. With no order and no Job cost line picked, Base works out its cost code from what it is for and puts it on the one trade line that carries that code: a ceiling access panel goes on Ceilings + Partitions. This is the same whether the bill came through the assistant, the Documents tab or one of these forms. When two trade lines carry the code, or none does, it lands with No trade, and approving it asks you to pick one.

Record a bill or cost by hand

  1. On Cost Entries, press Add cost, then Other cost under No paperwork.
  2. Pick the Order the bill pays, or "No order — standalone cost". If the amount is more than the order has left, the form warns that it will be flagged over its order.
  3. Pick the Budget Line (or "No trade — outside every trade figure"), the Type, the Supplier, a Description, the Amount (ex GST) and the GST on the invoice as the invoice states it. Left blank, the GST is assumed at 10% for the life of the row.
  4. Choose the Invoice file if you have it.
  5. Press Add. The cost counts toward the job immediately. If you hold the approve-costs permission and attached the invoice file, it is approved as you save it and the next payment run can select it; a bill saved without its invoice waits for it; otherwise it counts against the job but is Not payable until someone who can approve ticks it. A bill that matches its order, its delivery and your policy limit approves itself as it lands, and the page says so.

Approve what came in automatically

Bills pulled from Xero, read off an emailed invoice, or added from a scanned receipt arrive Awaiting review. They are not counted in Actual yet. A banner at the top of Cost Entries says how many wait and for how much.

  1. Filter to Awaiting review (or press the banner).
  2. Tick the approve box on a row to put the cost on the job and make it payable. Or press Approve all N to approve the queue in one go; it stops at the first bill that fails and says which.
  3. The same tick, unticked, takes a bill back out of actuals.

Approving from Money → Decide runs exactly this tick, as you.

Attach the invoice to a bill

A bill is approved and paid only with its invoice attached. Until then it still counts toward the job, and its row shows Invoice missing · Attach.

  1. On Cost Entries, press Invoice missing · Attach on the bill's row. Pressing Approve on a bill with no invoice opens the same box.
  2. Upload the invoice, or pick it from the files already on the job (an invoice you sent in chat or that came by email is usually there).
  3. Press Attach invoice. If you opened it from Approve, the bill is approved as soon as the invoice is attached.

When you add a bill by hand, choose the Invoice file on the form and it is attached as the bill is saved.

Clear a held bill

A machine-read bill that would take its purchase order past its value is Held. It is never approved on its own. The Held banner names each one with the order and the amount over. Vary the order (or move the bill to the right order), then approve it. Every held and unmatched bill across all jobs is also on Procurement → Pending review.

Record what the orders say should be here

The Cost Entries tab carries a badge when Base has suggestions from this job's orders: goods receipted with no bill, an order marked completed with nothing posted, a certified subcontractor claim with no cost entry, a bill on the job that pays an order nobody linked it to, an order on no budget line. Each suggestion says why, in facts that were read, with one button beside it; Edit first opens the ordinary add form with the draft in it. Nothing is written without a person pressing something, and a recorded cost is not approved by this panel.

Read the job's true value

The panel shows four figures, ex GST:

  • Contract: the contract sum plus approved variations.
  • Expected final: what the job will have cost by the end — spent + owed + still to buy. Under it, how much of that is still to buy.
  • Margin at completion: the contract less the expected final, as a figure and a % of contract, with how far it has moved since last month.
  • Spent: everything the job has cost the business so far. That is outside bills and certified subcontractor claims, your labour at cost rate, stock and your own plant, plus what is incurred but not billed yet: bills awaiting approval, work built on orders and not invoiced, hours not yet approved, and hired plant whose bill has not arrived. The part not billed yet is named under the figure.

After overheads (the default) adds the job's share of overheads to the cost, at your recovery % from Settings → Finance. Before leaves it out. The panel remembers your choice on this device.

Press What's in it to open the rest: Earned to date (the value of the work done — measured progress where a trade has a % complete, otherwise cost against the expected final), Margin to date (earned less spent), then the spent figure line by line. Each line opens to the rows behind it: the bills, the weeks of labour, the stock picks, the plant days. In Accountant mode the money strip with Committed, Accrued, Actual, Paid and Due is under Committed, accrued, paid and due.

A figure that is not known says not known, never $0: a job with no budget has no earned value or margin, and a job with no contract sum has no margin.

Read a trade's row

  • Budget: what the trade was meant to cost — its estimate section, plus its approved variations.
  • Owed: what the trade's issued orders and signed subcontractors still have to bill, after the bills already in.
  • Spent: what the trade has cost so far. When part of it is not billed yet (a bill awaiting approval, hours not approved, work done on an order and not invoiced) the row says so under the figure.
  • Expected final: spent + owed + still to buy. Over/under is that against the budget.
  • In Accountant mode, Still to buy: budget nothing has been ordered or spent against, plus the extras named on the line, less any still-to-come figure accounts set.

The totals row is the job: the same numbers as the headline. A trade whose bills or orders sit on no trade is counted in the job's figures and in no trade's; Needs doing names them.

See the job on a past day

  1. Pick a day in As at on the panel.
  2. The figures show the job as it stood that day. For a day Base saved, the panel says so. Earlier than that, it rebuilds the day from the bills, orders, timesheets and claims dated on or before it, and says it was rebuilt. Work earned is then the work claimed by that day, and a forecast counts only if it was set by then.
  3. Press Today to come back.

Work through Needs doing

Needs doing sits under the True value panel whenever the figures are waiting on something. Each row is one thing, with one button that takes you to it, and the row goes once it is done. The first three show; Show more opens the rest. It lists:

  • no contract sum, or no budget, so there is nothing to measure against
  • bills awaiting approval, bills you typed that nobody with the approve permission has ticked, bills on hold (over their order, from the wrong supplier, not delivered), and costs with no invoice attached (the button opens the invoice drop)
  • hours worked and not approved, and hours by someone with no cost rate, so they can't be priced
  • costs or orders on no trade — counted in the job and in no trade — and bills whose GST is assumed
  • a variation that was built or started before the client agreed
  • a trade whose hours are over its estimated hours by more than the tolerance (15% to start), plant used with no rate, no overhead % set, labour, stock or plant on no trade for more than the set number of days (7 to start), a trade whose expected final is more than 10% over its estimate, or a still-to-come figure nobody has revisited
  • the estimate having moved since the budget was built (on a won job, that is the finding: a cost after the win is a variation)
  • in Accountant mode, the extras accounts have not reviewed and stale still-to-come figures

To change the tolerances for this job only, press This job's settings in the list. An admin can also give the job its own overhead % there, for a cost-plus job whose fee covers your overheads, with the reason.

Move labour, stock or plant to another trade

Your own costs place themselves: labour on the trade picked on the shift or the person's trade, stock on its unit's line, plant on the trade picked when it was logged. To change where one landed:

  1. On Cost Entries, press Internal to show only your own costs.
  2. Press the move button at the end of the row.
  3. Choose Another trade, pick the trade, and leave All of it ticked, or untick it and type how much (a split).
  4. Say why, and press Move it.

The amount never changes, only the trade it is charged to. The move is kept with your name and the reason. To change the hours themselves, fix the timesheet.

Write a cost of your own off to overheads

For a training day or a callback the client won't pay for: open the row's move button, choose Off the job, to overheads, say why, and press Write it off. It leaves this job and goes on your overhead job with the reason. Needs the set-forecasts permission.

Log a plant or vehicle use

  1. On the panel, open What's in it → Internal costs and press Log a use beside Own plant and vehicles.
  2. Pick the item, the day, how many days, hours or kilometres (the item's own unit) and the trade. Leave the trade blank for the job's labour or prelims line.
  3. Press Log it.

The hourly run charges it to the job. An item the business owns is charged at its internal rate, and an employee's own vehicle at its allowance. A hired item accrues at its hire rate until the hire company's bill arrives and is matched to it; then the bill is the cost. A contractor's item is recorded and charges nothing.

File a variation line under its trade

An approved variation's cost goes onto its trade's budget line by itself. A part no trade fits gets a line of its own, marked VARIATION · NOT FILED, and a banner above the budget counts them. Until it is filed, an order or bill on the trade line is counted twice in the expected final.

  1. On Budget Lines, find the line marked VARIATION · NOT FILED.
  2. Open File under… under its name and choose the trade. Base's best match comes first, marked (suggested).
  3. Its budget, and any order or bill on it, move to that trade line, and the variation line disappears from the table. Press Undo in the message to put it back. Later, open the trade line and press Undo beside the filing in its adjustments.

Filing needs the set-forecasts permission.

See every variation and what it does to the money

The Variations tab lists every variation on the job, whatever its status, with what the client pays for it, what it costs you, the margin between, and where its cost sits in the budget. You raise and edit variations in the Variation Register; this tab is their cost view.

  1. Open the Variations tab, or press Variations → in the Anticipated strip above the tabs.
  2. The band at the top totals four groups: Approved (in the revised contract), With the client (not in it until they say yes), Not sent (drafts and variations on hold) and Absorbed (the cost you wear, not a price). Press a figure to show only that group; press it again, or Show all, for everything. Rejected variations have their own switch under the band.
  3. Each row shows Sell and Cost ex GST, the Margin in dollars and as a share of the sell, Cost sits on (the trade line holding its cost), and At risk (work done before approval, or approved money not yet claimed, with how long it has waited).
  4. Press the VO number, or the arrow at the end of the row, to open that variation in the Variation Register.

Cost sits on reads Own line · not filed when the cost still needs filing under a trade (see above), On no budget line when an approved variation's cost is missing from the expected final, and Not in the budget yet for one the client has not approved.

Change a line's cost code

Open the line and choose under Cost code. A variation's parts are matched to trades by cost code, so coding a trade line helps the next variation land on it. Needs the edit-costs permission.

Turn on Accountant mode

Press Accountant mode at the top of the page, or Alt+A. It stays on in this browser until you turn it off, and the same switch works on every finance page. In it:

  • The table adds Still to buy and Var %; the By Cost Type, By Cost Code, Schedule of Values and CVR tabs appear, and so do the committed-accrued-paid strip, the CPI badge, the anticipated-variations strip and the banner about the estimate having moved.
  • Every figure is underlined. Click one to see how it is worked out.
  • Needs doing adds each extra a project manager added that accounts haven't reviewed, and each still-to-come figure that's gone stale. Click one to open its line.
  • Open a line for Everything else still to come, % complete, the line's budget moves, and the working behind the figure. Close month, Reconcile to estimate and the CVR tab appear too.

Accountant mode only changes what you see. Each tool still needs its permission.

Set what is still to come on a line

In Accountant mode, open the line. Everything else still to come is everything left on the line apart from the extras listed above it. Leave it blank and Base works it out from the budget not yet ordered or spent, bills awaiting approval and progress.

  1. Type the figure, ex GST, and say Why. A figure that lowers the expected final needs a reason.
  2. Set % complete if you measured it.
  3. Press Save. The extras stay on top of your figure, and saving marks them reviewed.

Work it out drops your figure and goes back to the calculated one. The project manager sees "Accounts:" and your reason under the trade.

Close the month

In Accountant mode, on Budget Lines or CVR, press Close month (set-forecasts permission). Pick the Month, read the Movement since the last close for each line, add a note, and confirm. Every line is frozen at the cut-off, and each line's expected final and its movement are recorded, with a reason for every reduction. The CVR tab shows the closed months.

Whether Base also asks you to close each month, on Money → Decide, is a switch under Settings → Finance → Month close. It is off unless you turn it on, or your business has closed a month before. When it asks, it asks once for the whole business: one decision naming every job with a month to close, the most overdue first. Approving it closes each job's month in turn; if one cannot close — a line's forecast fell with no reason on it — the ones before it are closed, the row says which job stopped it and why, and approving it again carries on from there.

Correct the contract sum

Once the job is won, the contract sum is locked. If the client is paying more or less, raise a variation instead. If the figure was entered wrongly, press Correct the contract sum under Revised sum at the top of the page. Enter the right figure, ex GST, and say why it was wrong in at least ten characters. This needs the Unlock a won estimate permission, which an admin turns on per person.

The correction is recorded against you and shown when anyone explains the figure. It moves the revised contract, the expected margin, WIP and what is left to claim. The budget and the schedule of values stay as they were built at the win.

Under Evidence, press Attach the signed contract or quote to keep the document the right figure comes from with the correction. It is optional; the list of recorded changes then says evidence attached.

Record a bank guarantee or bond

On Securities, pick Held from subs or Given to client, then:

  1. Press Add security. Drop the guarantee or bond on the form, or type it in. Base reads the type, whether you gave it or hold it, the issuer, its number, the amount, who it is in favour of and its dates; each value read off the file is marked read.
  2. Check them and press Confirm and save. The security is in the register with its document. In place of cash retention is ticked to begin with; untick it for a security that sits beside retention rather than replacing it. A cash security is one of the types.

A guarantee or bond needs its issuer — the bank or insurer that stands behind it.

See how a figure is worked out

Hold Alt (Option on a Mac) and click any figure on the page, or turn on Accountant mode at the top and click it. The audit panel lists what makes the figure, each part linked to where it came from:

  • A line's columns. Budget is the figure the line was seeded with, then each approved transfer, risk release or reconcile by name. Committed lists each issued order (its share of an order split across lines). Actual lists each bill that counts, and sets aside the ones awaiting approval and the voided ones. Remaining shows what each order has left to bill, less any bill on the line that names no order. Uncommitted names the estimate lines not yet ordered, by labour, material, subcontract and plant. Both are columns in Accountant mode. Expected final is what is billed, plus what is left on orders, plus what is still to come, plus each extra by name, with who set the still-to-come figure and why when accounts did. Over/under is the expected final less the budget.
  • The totals row and Cost Summary. One row per line, each opening its own working in place.
  • The True value panel. Every tile and every row of What's in it, for today's figures. Earned to date is each measured line's budget × its %, over the work budget, times the revised contract (or actual ÷ expected final when nothing is measured). Cost to date lists outside bills, your own labour, stock and plant, then what is incurred and not billed — bills awaiting approval, hours not yet approved, hired plant — and, after overheads, the overhead share; each row opens to its entries. Margin to date and At completion show earned (or the revised contract) less cost less the overhead share, with the % beside them, and say when the figure is before overheads. Overhead share is the recovery % × the cost (or revenue) it is recovered on, and says where the % came from. A past day's figures (As at) come from a saved or rebuilt position and are not audited.
  • The money strip. Committed, Accrued, Actual, Paid and Due. Paid and Due list each bill with what was paid and when it is due.
  • The strips beside the table. Anticipated lists each variation with the client at its price and how long it has sat there; the work done on unapproved variations is each one's price × its % built. Engaged, no order names the trades with signed subcontracts not yet ordered. Extras named on the lines lists each extra with its trade and whether accounts have reviewed it. Committed to no trade lists the issued orders on no budget line, Unassigned the counted costs on none. On a line, the % complete chip opens the measured %, what it earns, the CPI and where the line ends at that rate; in the line's drawer the accrued figure opens its bills awaiting approval and the measured work on its orders not yet invoiced.
  • The SOV tab. Each line's scheduled, claimed to date, remaining and %, and the totals — the same working as the Invoicing tab's schedule.
  • The Variations tab. Approved and With the client open their variations by name.

Each order, bill or variation links to its document where Base holds one, or to the bill in Xero. If a stored figure has drifted from its bills or orders, the panel says by how much; the hourly reconcile corrects it.

Press Ask Base about this figure to take the figure into the chat and work through it with the assistant. Under Questions about this, click a question that fits the figure, such as how to log a bill, add a receipt, raise a purchase order or update a forecast. It is asked in the chat for you, and where this guide has the steps the answer follows them.

Record the project outcome

On a completed job, Project Completion sits at the foot of the page. Press Record Project Outcome, type the Actual margin % (on the price) the job made, and press Save outcome. The box starts from the quoted margin on the price, which Base records beside it from the quote's mark-up. The final contract sum, approved variations included, is recorded too. It needs Projects edit. If it cannot be saved, the page says why.

Filter the cost entries

The chips above the table: All, Not payable (counted against the job but no payment run can pick it up until approved), Awaiting review (machine-read, counts toward nothing until approved), Held, Approved (approved and unpaid — what the next payment run can select), Paid, No trade (on the job, on no budget line — outside every trade figure), and Internal (your own labour, stock and plant). Your own costs are never in Paid: nobody pays a bill for them.

What happens on its own

  • An approved variation's cost is added to its trade's budget line. The line's adjustments say which variation, how much and how it was matched. Un-approving takes it back off; marking it absorbed keeps it.

  • A variation line still on its own is filed on the hourly finance run once Base can tell its trade: by its cost code or the trade's name, or by Base's own judgement when it is sure. A line you put back with Undo is never filed again on its own.

  • Approving a bill recomputes the budget line's actual and expected final. The bill is then pushed to Xero as a bill within a day, on the cost code's account with the job's tracking option.

  • A bill links to its order when Base can say so without guessing — the PO number is on the bill, or the supplier has one open order on the job, or one order with room for the amount. Once linked, the order's invoiced and remaining figures move on the Purchase Orders tab.

  • A bill approves itself only under the three-way match, and only with its invoice attached: it fits what its order has left, is from the order's supplier, the delivery is recorded and it is under the limit set on Settings → Finance → Automation. The basis is recorded as a three-way match, nobody's tick. An over-invoiced or unmatched bill never does.

  • A new machine-read bill is announced to the reviewer in the inbox.

  • Orders that missed their budget line are placed on the hourly finance run when Base can tell which line they belong to, by the estimate section or the trade's name ("Mechanical / HVAC" goes on Mechanical Services). The bills on those orders follow them. An order Base cannot place is named on the Money page, and Job Costs suggests a line for it. Base never moves an order a person has put on a line.

  • Hours worked and not yet approved show as Provisional labour. The tile beside Actual shows what those hours cost at each person's rate, and the line they will post to shows +$X provisional under its actual cost. Alt+click either to see the hours by line. They count in the expected final like a bill waiting for approval: inside the line's labour budget they change nothing, past it they raise it. They are never actual cost. N h to approve under the tile opens Timesheets to approve them.

  • The hourly finance run checks the job's baseline and puts one item in your standup for each thing it finds, opening this page: a contract sum that is not the quote the client accepted (or the last one sent), by more than a dollar; and a budget that is 98% or more of the contract (approved variations included) — no margin from day one, usually the estimate's prices read as cost. Each clears itself once the figures agree; one you dismiss is not raised again until the figures change.

  • A corrected contract sum is told to the admins — before and after, the reason, and who made it (not the person who made it).

  • A security is watched from the day it is recorded: Base tells you 30 and 7 days before it expires, and marks it expired when it lapses.

  • A credit read off a credit note, or pulled from Xero, is announced to the head PM (the admins when the job has none): it reduces the job's cost once someone approves it. A credit you typed counts at once and is not announced.

  • Supplier credits raised in Xero come in with the bills. A credit note in Xero that carries the job's tracking lands on Job Costs as a negative cost, on the bill Xero allocated it to when Base has that bill. A credit Xero voids stops counting.

  • A levy or fee recorded unpaid is announced to the finance contacts and admins, with the amount and when it is due.

  • The QLeave check. Two weeks after a Queensland job of $150,000 ex GST or more is won, if nothing on its costs is the QLeave levy, one item in your standup says so and opens this page. It is raised once per job; a levy notice already filed on the job's Documents is asked for there instead. A job where you are the trade contractor or supply only is left alone.

  • Your own costs place themselves on the hourly finance run. Labour or plant that posted before the job had a budget goes onto the trade posting would pick now, split by person where the week holds several trades. Each placement is logged. Stock Base can't place stays on no trade, and Needs a look raises it after the set number of days.

  • Plant uses are charged on the hourly finance run, at the job's own rate for the item from its date, else the item's rate. A use already charged is never repriced. A hired item's uses are matched to the hire company's bill by the company's name on the bill, and stop accruing once matched.

  • Each job's true value is saved every day with the money position, so a past day shows what the panel said on it.

  • Adding, closing or dropping an extra recomputes the line's expected final, so WIP, the Money page and the morning brief read the new figure.

  • A bill on a trade is matched to the estimate lines it names. When every word that matters in a line is on the bill ("Ceiling access panel 600×600 flush…"), or the bill's few words are all in one line ("GPO outlets"), the line is ticked off under Outstanding — not yet ordered. A bill on an order that names its lines is left to the order, and a line an order names is never matched this way.

Things that surprise people

  • The contract sum can't be edited once the job is won. Edit project shows it greyed out. A change the client pays for is a variation, and a mistake is corrected on Job Costs with a reason. Every change since 9 Oct 2026 is recorded, and Alt+click on the figure shows them.

  • The overhead share is shown, never posted. It is in no cost entry, no WIP journal and nothing sent to Xero. Actual cost and the books stay what the job spent.

  • Labour, stock and plant rows can't be edited or deleted. Their amount follows the timesheet, the stock or the plant booking. Fix those, or move the charge. Deleting a posted labour week would leave its hours never charged again.

  • Labour never shows in payment runs or goes to Xero as a bill. Wages are paid through payroll. Before 22 October 2026 a posted week of labour could have been offered to a payment run as a bill from "Internal labour".

  • Amounts are ex GST everywhere on this page. A $1,100 invoice with GST is a $1,000 cost. The GST you type on the invoice is kept beside it.

  • Owed comes from issued purchase orders and signed subcontractors. A draft order is not a commitment and does not move the number. A signed subcontractor with no order yet is owed too, and the trade's drawer says so.

  • Spent is more than the approved bills. It includes what is incurred and not billed yet — a bill awaiting approval, hours not approved, work built on an order and not invoiced — so the job's cost does not jump the day the paperwork catches up. The row names that part. Actual cost in the books, the WIP and Xero is still the approved bills only.

  • Every figure on the page is the same calculation. The trade rows, the totals row, the headline, the Money page, the WIP and the reports read one function, so they agree. A figure that differs between two screens is a bug, not a view.

  • A bill without its invoice counts, but can't be approved or paid. The row says Invoice missing, the trade's drawer says No invoice, and Approve all leaves those bills in the queue and says how many are waiting. A bill pulled from Xero has its invoice in Xero, so it never waits. Wages, stock, plant and costs added as Other cost need no invoice.

  • A bill approved before 24 October 2026 without its invoice is held back from payment runs until the invoice is attached. The run lists it under what it held back, with the reason.

  • A cost you typed yourself counts at once but may not be payable. The Not payable chip is the tell; someone with the approve permission has to tick it before a payment run will pay it.

  • A tick under Outstanding means the line is paid for, not merely mentioned. A bill Base matched by its words ticks a line only when it covers at least half of it; a smaller bill shows part-invoiced $150 of $12,000 and the line stays on the list. A tick you made with Tick off always stands. A Xero bill nobody has approved yet ticks nothing.

  • "Not known" is not zero. A job with no budget shows Earned to date, Margin to date and the Money page's Unbilled as not known, because there is no percent complete to earn against. Set up the budget and they appear. A cost-plus job's margin tiles read cost-plus: the fee is the margin.

  • The file you attach as the invoice has to be an invoice. Attach invoice and Attach quote accept only a document filed as that kind (an invoice, receipt, claim or credit note for a bill; a quote, tender or price list for an order) and say why when they refuse. Re-file the document with the right type, or attach the right one.

  • Replacing the budget from the estimate loses hand-edited figures. Reconcile instead keeps them and proposes the differences.

  • An absorbed variation shows no sell and a negative margin. The client pays nothing for it, so its whole cost comes off your margin. The Approved total on the Variations tab never includes it.

  • A trade's budget includes its approved variations, so it can sit above the estimate with nothing wrong. The banner about the estimate changing leaves them out, and Create from Estimate is refused while any are on the budget: use Reconcile instead.

  • A saving on an order doesn't show by itself. The worked-out expected final never drops below the budget, so a trade let for less than its allowance still shows the allowance. Accounts can set the line's still-to-come figure in Accountant mode once the trade is covered, and the saving shows in Over/under.

  • An extra goes on top of the budget, not inside it. A $50,000 trade with nothing ordered and a $5,000 extra expects $55,000. Only add costs the budget doesn't already cover.

  • An extra keeps counting until someone says it's in an order or bill. Raising the order elsewhere doesn't close it by itself. The line asks about a newer order, and until it's answered the cost is counted twice.

  • Ticking a line off doesn't change any figure. The bill already counts against its trade whether or not it names a line. A line ticked off for less than its estimate still leaves that budget in the expected final. If nothing more is coming, accounts set the still-to-come figure in Accountant mode. A tick is also not a payment: an unapproved bill shows awaiting approval, a paid one paid.

  • A package invoice ticks nothing off by itself. "Supply and install plastering, framing and ceilings" names no single line, so Base leaves it for you to tick off line by line.

  • Provisional labour moves to Actual when the hours are approved, on the next hourly finance run. It is never counted twice. A person with no pay or cost rate is left out and counted under the tile, so set their rate.

  • A bill on no budget line is outside every trade figure. It is on the job and nowhere else until you give it a line.

  • Uncommitted is plain on every row. It is estimated scope nobody has ordered yet, which is normal early in a job; the pane at the top names the trades that need a look, and a line over its estimate shows in red under Variance.

  • A bill is approved only once it names its trade and cost code. Base takes them from the order it pays, or works them out from the job, and writes them onto the bill. When it cannot, the tick is refused with the job's trades to pick from, and a bill you typed yourself is saved but left Not payable, with the page saying why. Give it a Budget Line and tick it again. A bill the three-way match would approve waits for a person in the same case. Hours already worked, a certified subcontractor claim and a bill Xero already holds are never stopped this way.

  • The quoted margin on an outcome is a margin on the price, not the quote's mark-up. A 30% mark-up is a 23.08% margin. Outcomes recorded here before 17 October 2026 stored the mark-up, so their quoted margin reads higher than the actual it is compared with; they were left as they were.

  • A supplier credit shows as a negative cost. It sits on the bill's trade line and order and lowers both. It is never approved by the three-way match, and it is not pushed to Xero as a bill: enter the credit note in Xero against the supplier, and the next pull matches it to the one here.

  • A deposit or pro-forma invoice is not a cost here. It is paid against its order, on the order's Paid ahead panel, and becomes cost when the tax invoice arrives. See Purchase orders.

  • A budget line below zero is a credit, and it forecasts its credit. A cost-saving credit from the estimate, or an omission variation, lowers the job's forecast by its amount until you change the budget. A supplier credit note booked to the line is that credit, not a second one; a bill booked to it is added on top.