Money in Base moves through a small number of records, and once you know what each one means the rest of the product follows. This page is the model. The pages after it are the how-tos.

The four things to know

1. A progress claim has two numbers, and they are meant to differ. The work value is what the claim represents: the value of work done this period, ex GST, before retention. The total is what the client is asked to pay: work value, less the retention held on this claim, plus GST. Base's profit and loss and work-in-progress figures count the work value as revenue. The Claims & Invoices page and the client's portal show the total. If you ever see the two side by side and wonder why they differ, that is why.

2. Costs are ex GST, and a machine cannot spend your money. Every cost on a job is recorded ex GST. A bill a person types in counts against the job straight away. A bill a machine read — pulled from Xero, read off an emailed invoice, added from a scanned receipt — arrives awaiting review on the job's Job Costs page. It counts toward nothing and reaches no payment run until a person approves it. If a job's actuals look low, look at the review queue before assuming something is broken.

3. Xero is downstream. Base decides the number; Xero receives it. A claim goes to Xero as a sales invoice built from the claim's own lines, with retention taken off as a negative line, on the accounts you have chosen. Payment status, part payments, voided invoices, bills raised directly in Xero and new contacts come back from Xero on their own.

4. The assistant proposes; you decide. Base's assistant will propose what to certify on a subcontractor's claim, draft a claim for finished work, match a bill to its order and assemble a payment run. On its own it never approves a cost, certifies a claim, approves a payment run, marks anything paid or issues a credit note. Those decisions land on Money → Decide, and the button is yours.

Where each thing lives

I want to…PageGuide
See where the business is at, in plain words — free after obligations, runway, profit, decisionsMoneyMoney
See every order across every job, what is late, held bills and bills with no orderProcurementProcurement
Raise, send and track a progress claimClaims & Invoices, or the job's Invoicing tabClaims and invoices
See what a job was meant to cost, has committed, and has costThe job's Job Costs pageJob costs and supplier bills
Get a supplier bill or receipt onto a jobJob Costs, or ReceiptsJob costs and supplier bills, Receipts
Deal with a subcontractor's payment claimThe job's Job Costs page, Subcontractor Claims tabSubcontractor claims
Pay approved bills and certified claims from the bankPaymentsPayment runs
See what has synced with Xero and what counts in reportsXeroXero
See who owes you, what you owe, and whether jobs make moneyReports, CashflowReports and cashflow
Turn inbox receipts into job costs or a tax recordReceiptsReceipts
Set the money rules — terms, bank, GST, targets, what issues or approves itselfSettings → FinanceFinance settings
Decide where each cost code posts in Xero, and approve chart changesSettings → Chart of AccountsChart of accounts
Keep the trade codes every cost rolls up bySettings → Cost CodesCost codes
Understand what the assistant does with money on its own—Automations and the assistant

Tutorials

Tutorials walk four scenarios end to end: a claim from raised to paid, a supplier bill from arrival to paid, a subcontractor claim under the Security of Payment Act, and a month-end review.

Setting up finance for a new business

Do these once, in this order. Each takes a few minutes. All of them need an organisation admin.

  1. Connect Xero on Settings → Integrations, then choose the accounts claims and bills post to on the same card. Until you do, Base uses its Australian defaults and says so. See Xero.
  2. Set payment terms on Settings → Finance: how many days your clients have to pay a claim, how many business days you have to answer a subcontractor's claim, and how long after a cost is incurred the cash leaves for each cost type. Everything downstream reads these. See Finance settings.
  3. Enter your bank details on Settings → Finance → Bank: bank, BSB, account number, account name and the APCA user id your bank gave you for batch payments. Payment runs cannot build a bank file without them.
  4. Check your cost codes on Settings → Cost Codes. They are seeded for you. If your accountant wants materials and subcontractors on different Xero accounts, set the account on those codes (or on Settings → Chart of Accounts).
  5. Add bank details to suppliers and subcontractors as you go, on their record in Contacts. A payee without them is held back from payment runs with the reason, never silently skipped.