Workshop
The whole shop floor on one screen — every released unit with its next step, its joiner, its hours, its stations and when it is due.
What it is
The Workshop board is the whole company's shop floor on one screen. It lists every joinery unit a project manager has released to the workshop, across every job: where it is in production, its one next step, who is making it, the hours logged against it and when it is due to leave. It is for the foreman and the joiners. The foreman runs the floor from here: move a unit on, give it a joiner, print its labels. A joiner also moves a unit on at the workshop QR when they sign out (Machining done, Assembly done and so on, one stage at a time).
Before you start
- The Workshop module must be on for you (Settings → Team modules). Moving units through the workshop needs Workshop or Manufacturing edit.
- A unit appears here only after it is released on its job's Manufacturing page, which needs both approvals of its drawing and a price.
- The By station view needs the shop's stations, set up under Settings → Machines, tools and stations.
- To give a unit a joiner, the joiners need to be crew members (Delivery → Crew), the people who sign in with a PIN.
How to
See what is on the floor
- Open Workshop from the nav.
- Read the five tiles: Released, In production, Ready to dispatch, Installed and Overdue. They count the units after your filters.
- The Units tab lists every released unit: its tag and name, the job, its Track (the same strip as on the job's Manufacturing page, with the four Making dots and its flags, such as Overdue or Over hours), its Next step, its Joiner, the hours logged against the hours estimated, and when it is Due.
Move a unit on
- Press the unit's Next button, for example To assembly or Ready to dispatch.
- The unit moves one stage. If it cannot, the reason shows above the table, for example that its drawing is not approved or its materials are still to come.
- A step that happens on the job's page, such as receiving materials or crating, opens that page on the right tab.
Give a unit a joiner
- In the Joiner column, open the unit's joiner and pick the crew member making it.
- That unit now comes first in their list when they sign out, so their hours land on it.
Reschedule a unit
- In the Due column, press the unit's date and pick a day in the calendar; it saves as soon as you pick.
- It is the unit's own dispatch date from then on. A unit with no date of its own shows its job's date under the box.
Print a unit's labels
- Press labels at the end of the row.
- The part labels open ready to print on a 100 × 50 roll. Add
?layout=a4to the address for A4 sheets of 14.
See the floor by station
- Press the By station tab.
- Each station lists the units whose next unfinished step is there, marked started or waiting. Units through every station are listed apart, and so are units released before the stations were set up.
Narrow the list
The toolbar under the tabs holds the search and four filters. It shows on Units, By station and Gantt; the Crew tab plans people, so it has none.
- Type in the search box to match a tag, name or job.
- Open Any job, Any station, Any status or Any joiner (a crew member, or a login marked "(login)") and pick one. The chip lights while it filters, and the tiles and the list update together.
- Clear puts every filter back.
Read the production Gantt
- Press the Gantt tab and choose Day, Week or Month at the end of the toolbar.
- Each bar runs from the day the unit was released to the day it is due. Overdue bars are flagged.
- To move a unit's dispatch date, drag the right end of its bar. The new date shows as you drag, and saves when you let go.
Put people on stages (Crew)
- Open the Crew tab. Each row is a person on your workshop crew; each column is a working day. A day shows the stage hours booked on that person against the hours they have that day: their weekly hours over five, or nothing on a day of approved leave.
- Units to put on someone lists each released unit at the stage it is at, with that stage's hours.
- Drag a unit onto a person's day. On a tablet, press the unit, then press the day. The person is put on that stage, for that day, with the stage's hours. The first person on a stage is its lead; anyone after is a helper.
- A day booked past what the person has turns amber and their row says Over-booked.
- A day where a stage is booked past what its stations run shows a warning under the date, for example Assembly 10h of 7.6h: two people on the one bench that day. It needs each station's operation and daily hours set in Settings → Machines, tools & stations.
- A booking or unit with a warning triangle has stalled, gone over its hours or been held up. Hover over it to see which.
- Press the x beside a booking to take them off it. ← Earlier and Later → move a week at a time.
You can also put people on a stage from the unit's own page: Assign on the stage's card.
See what the team worked on
- Open the Crew tab. What the team worked on sits under the crew board. Pick the day beside its title (it opens on today).
- It lists each person who ticked their work at sign-out on that day, with their paid hours split across what they ticked, and whether each is done, part done or blocked.
- People who signed out without ticking anything are listed underneath. Base doesn't fill anything in for them.
What happens on its own
- The board refreshes itself when a unit changes, whether someone moved it here, on its job page, by a label scan, or the assistant did.
- Hours logged come from the units people tick at the workshop QR when they sign out (a stage button or Worked on it), added up as the shift closes and re-checked every night, so a supervisor's fix to a shift shows the next day.
- Each job's share of a shift is divided across the unit stages it was ticked to, and each stage's hours land on that unit's own joinery budget line when the week is approved and posts. Time ticked to no unit stays on the job's labour line.
- Whoever presses Start on a stage at a label is put on that stage.
- A person put on a stage sees it under Your units on their own page, with a link to the unit's label page.
- A label scanned at a station marks that unit's step there started, and done once every part is through. The unit's panel shows how long each step took.
- A problem reported at a station, or a unit reaching Ready to dispatch, sends a notification to the people who act on it.
- Every night Base checks each stage that is under way:
- Stalled. A stage with no scan, tick or hours on it for two working days is flagged Stalled on its unit. The job's foreman and everyone who runs the workshop get it in Needs you, once a day while it stays quiet.
- Over hours. A stage whose logged hours pass 120% of its estimate is flagged Over hours, and the same people are told once.
- You can change both lines under Making rules in Settings → Machines.
- A stage that can't start because its shop files aren't filed is flagged files missing on its unit. So is a stage whose files failed to file at release. File them from the unit's page.
- A stage ticked done at the workshop sign-out without its photo reads photo owed on the unit's page. The foreman is told in Needs you.
- A unit whose hours left won't fit before its due date is flagged Late. Under its due date it shows finishes ~ with the day Base expects it done, counting the hours left on its open stages over a working day.
- Each job's Manufacture task on the programme moves with its stages. It never reaches 100% on its own: a person marks it complete.
- If the morning workshop report is on, it also lists:
- the stages closed the day before, with their hours against the estimate;
- photos taken on stage lines, to check;
- what needs a look;
- who is booked on which stage today.
Things that surprise people
- Due is the unit's own dispatch date, or its job's dispatch date when it has none ("job" beside the date). A unit with neither is never overdue.
- Working days are Monday to Friday in your company's time zone. A stage left on Friday afternoon is not stalled until Tuesday night's check.
- A stage that finished over its hours drops off the warnings once it is done. The morning report's closed stages show it.
- Hours split by what a person ticked never change their timesheet hours.
- A unit released before the stations were set up has no station steps. Pull it back and release it again on its job's page to lay them out.
- The list stops at 500 units. A company that has released more than that at once sees the earliest-due 500.
- Hours typed on a unit stay as typed — the nightly count only updates a unit whose hours it worked out itself, or that has none. A unit given to one crew member is theirs, whatever names match.