Handover

Practical completion, the DLP, the handover pack, retention release.

What it is

The end of the job on one page: declare practical completion, keep the defects liability period and the handover checklist, record warranties, generate and send the PC certificate and the handover pack, release retention, record the outcome and close the project. A stage line (PC declared, Pack issued, DLP running, Final settled, Closed) shows where the job is. The project manager and admins act here; everyone else reads it.

Before you start

  • Nothing to switch on. Declaring, editing dates, keeping the checklist and warranties, sending the pack and closing need an admin or team role.
  • The job is won and the work is substantially done. Open defects are shown to you before you declare.
  • Retention releases are real claims, so the job's claims are set up (see Claims and invoices).
  • The Retention figures and Release retention need the Claims & Invoices module, and the closed job's actuals feed needs Job Costs. Without them those parts say so; the rest of the page works as normal.
  • Generate PC certificate and Record outcome open forms on the page for someone with Projects edit, plus Documents send for the certificate. Release retention opens its form for someone with Claims & Invoices edit, with or without Projects edit. Without those, the same button asks Base to do it instead.

How to

Declare practical completion

  1. Press Declare practical completion. Enter the Practical completion date, the Defects liability (months) (defaults to 12), who it was Certified by, any Conditions (printed on the certificate) and Other outstanding items not logged as defects, one per line.
  2. Press Declare practical completion. If defects are still open, Base lists them and asks you to Declare with these outstanding; they are recorded as outstanding items and printed on the certificate.
  3. The DLP starts, the handover checklist is seeded from the project documents, and the PC certificate is generated. Edit dates, beside the page title, later changes the PC date and the DLP length or end date.

Keep the checklist and the warranty register

  1. Under Handover checklist, Add item: its kind (As-built, O&M manual, Warranty, Certificate, Compliance cert, Keys & access, Maintenance, Other), title, status (Missing, Collected, Included in the pack), who owes it and notes; attach a project document or upload one. Attach or Edit on an item does the same.
  2. Ask Base to chase the missing items drafts the chase emails for your approval.
  3. Under Warranty register, Add warranty: what is warranted, Given by (a subcontractor or supplier from Contacts), the length in months, when it starts, notes and the document.

Add a handover document or certificate from its file

  1. At the top of the checklist press Add document, then Manual, warranty or as-built (an O&M manual, warranty, as-built or care guide) or Certificate. Before practical completion, Add a handover document now is under the practical completion card.
  2. Drop the document on the form, press Choose a file, or on a phone Take a photo of it. Base reads what it is, the product or system it covers, who it is from and when its warranty ends, and shows them beside the file. Or type them in.
  3. Check the values and press Confirm and save (Save when typed in).
  4. The document fills the checklist item that is missing it (the one naming what it covers, else the standard item of that kind), or is added as a new item. A warranty, or anything with a warranty end date, also goes on the Warranty register, running to the date printed on it. A certificate fills the missing compliance certificate and is kept on the job's certificate register on Hold points.

Ask your trades for their handover documents

  1. Before practical completion, use Documents from your trades under the practical completion card. After it, use Ask the trades at the top of the checklist. Either way, press Ask the trades.
  2. Each trade on the job is listed: a business engaged on it, or sent an order on it. Tick what you want from each: Warranty, O&M manual, Compliance certificate, As-built drawings. The first three are ticked for you. Anything already asked shows asked and cannot be asked twice.
  3. Under each trade's name a line says whether they will see the request: someone there has your Base portal, it is shared with them but nobody has signed in yet, or nobody there has it. Where nobody has it, Share it opens their page in Contacts in a new tab, where you give them the portal.
  4. Set Wanted by and press Ask. Each request becomes an item, such as "Warranty — Sparky Co", on the trades panel (on the checklist after PC), marked Asked of the trade with the date. The message that follows says which trades will see it and whether anyone is emailed.
  5. A trade with your Base portal sees it in the portal's Handover tab and uploads it there. The item turns Collected, marked Sent by the trade in their portal. If they email it to you instead, press Attach on the item and pick or upload the file.

Add a trade's warranty to the register

  1. A warranty a trade sent shows Add to warranty register on its checklist row until it is on the register.
  2. Press it. The warranty form opens with the trade and the document filled in. Open the document, enter what it covers, how long it runs and when it starts, and press Add warranty.

Generate the PC certificate

  1. Press Generate PC certificate (Regenerate PC certificate once one is filed). A form opens under the buttons.
  2. It lists the open defects, which print on the certificate by themselves. Under Other outstanding items, add minor items not logged as defects, one per line; the conditions and items you entered at practical completion are already there.
  3. Press Generate certificate. It is filed on the job, linked to the closeout, and the checklist's certificate item is collected. Our side is signed if a signature is on file.
  4. Open it to check it, then Send it for the client's signature to send it for their counter-signature. or ask Base to do it hands the whole thing to the assistant instead.

Generate and send the pack

  1. Generate handover pack opens a chat where Base assembles the pack (telling you first what would print as "to follow") and files it against the closeout. Regenerate reruns it.
  2. Send pack to client (once a pack exists): tick the client contacts, add other addresses and a Cc, write a message, and optionally Show the pack and the warranty register on the client portal. Press Send pack. The PDF is attached, replies come back to the job, and the page records when and to whom it went.

Release retention

The Retention panel shows held to date, released, in draft and outstanding, with each release claim and its status.

  1. Press Release retention. A form opens under the buttons. If a release is already waiting on Money → Decide it says so. Releasing the same share here approves that one rather than filing another, and releasing the final balance also closes a practical-completion release still waiting there.
  2. Choose what to release: the Practical-completion share (your share of what is held, 50% unless your organisation set another) or the Final balance once the defects period has ended. Each shows what is releasable now, ex GST, or why it cannot be released yet.
  3. Releasing the final balance while defects are still open asks why. Holding the last of the retention is your leverage over them, and your reason is written on the claim.
  4. Press Draft the release claim. Base drafts the claim through the normal claims path, with GST added, and records it on Money → Decide as your decision. If an approval limit or a permission stops you, it waits there for someone who can approve it.
  5. Nothing is sent. Open Invoicing in the message that follows, review the claim and send it from there. A draft release is not released until it is sent.

Hold Alt (Option on a Mac) and click any retention figure to see how it is worked out. Held to date lists what each issued claim held back, and is the running figure stamped on the latest one. Released and In draft list each release claim. Outstanding is held less released.

Close the project

  1. Ready to close? lists the checks: practical completion declared, defects liability period ended, no open defects, retention released, final claim issued.
  2. When every check passes, Close project. When only open defects fail, Close with open defects… asks why (at least five characters) and records the reason on the closeout. Nothing else can be closed past.

Record the outcome

  1. Press Record outcome (Update outcome once one is recorded). A form opens under the buttons.
  2. Enter the Quoted margin % (it starts from the quote's markup, as a margin on the price), the Actual margin % if you have Job Costs, the Final contract sum (ex GST), the Project type and What we learned. Leave the contract sum blank and Base works it out as the contract sum plus approved variations.
  3. Press Record outcome. Estimate accuracy is finalised per section from the budget. The job is not closed: Close project does that.

Feed actuals to the rate book

Once the project is closed, Prepare from actuals compares each estimate line with the approved costs on its cost code. Review and confirm shows the lines whose actual unit rate can be proposed as rate-book evidence, and each section summarised as actual against estimate; untick anything whose quantity or scope changed on site. Only what you confirm is written, and no live estimate is repriced. See what was fed shows it afterwards.

What happens on its own

  • When the programme's practical completion milestone passes, or all the site work on the programme is ticked done, the head PM and admins are told practical completion is due, with a link here. Nothing is declared for you.
  • Declaring PC tells the head PM and admins, seeds the checklist from documents already on the job and generates the certificate; if the certificate fails, PC is still declared and the page tells you. The job's header then reads Handover & DLP, and the dashboard and Projects stop counting the job as active.
  • When the handover pack is put together, the head PM (the admins if there is none) is told it is ready to check and send to the client. Whoever put it together is not told.
  • With Tell the client at practical completion and share the handover switched on (Automations → Library, off until you turn it on), declaring PC emails each client contact who can still open the job the PC date and when the defects period ends. The button is the sign-in page with their address filled in, landing on their job in their portal (on its Handover page when the pack is shared). It also switches on Handover pack & warranties on the job's client portal. With the automation off, declaring PC shares nothing: switch Handover pack & warranties on yourself on the job's Client page.
  • With Draft a "How did we go?" email at handover switched on (Automations → Library, off until you turn it on), sending the pack after practical completion puts one task with the head PM carrying a drafted email to the client, asking how the job went with a link to a short review on their portal. Nothing goes until someone approves and sends it from the task. It is raised once per job, and the client's review closes it; the head PM is told the score.
  • With Draft a second "How did we go?" email when the defects period ends switched on (Automations → Library, off until you turn it on), the day the defects liability period ends puts a second drafted request on a task with the head PM, asking now that the client has lived with the work. It is skipped when the client has already said how the job went, or a drafted request has not been sent yet. A request that was sent and never answered does not stop it: that task closes as done and the new one takes its place. Once per job. Anyone can also ask at any time after PC with Ask for a review on the job's Client page.
  • Open defects, retention and the final claim are read live from their own pages; the readiness checks here are the same ones Close enforces.
  • When a retention release falls due (the first half at PC, the rest when the DLP ends), the release claim is drafted for approval on Money → Decide, and the head PM (or the admins, when the job has none) is told once, with the amounts and a link back here. Approving it raises the claim; sending it stays with you. Release retention on this page approves that same decision. The owner's 7am brief lists it too.
  • Retention still held beyond a final release claim after the DLP has ended (the final was cut short, or a later claim held more) falls due the same way: a release of the rest waits on Money → Decide, and the head PM is told once for each final release it follows.
  • DLP expiry letter prepares the letter closing out the defects liability period from the closeout's dates.
  • When a trade sends a handover document from their portal, it is filed on the job, the item is collected, and the head PM (the admins if there is none) is told which document, from whom, for which job.
  • If you set an item back to Missing (the wrong certificate, say) and the trade sends it again, the head PM is told again.
  • Documents asked of the trades before practical completion join the checklist when you declare it. A file already on a trade's item is not matched again by its name to the standard items.
  • Every morning after practical completion, a manual, warranty, as-built or maintenance schedule filed on the job in the last 30 days goes onto the checklist item still missing it, by its name, the way the documents on file at PC do. Each one shows in your ledger as done, so you can see what was filed and change it. A document someone already recorded, or one Base read as something else (a certificate, a bill), is left alone.
  • With Ask a subcontractor for their handover documents switched on (Automations → Library, off until you turn it on), the trade is also emailed what is still to send and by when, with a button into their portal. When nobody there has your portal yet, the email goes to their main contact and shares it with them. Once they have sent everything asked, nothing is emailed.

Things that surprise people

  • Retention comes back in two goes, at PC and at the end of the DLP, and both are claims through the normal invoice path. A release that is still a draft counts as neither released nor outstanding.
  • Raise the final balance first (a PC date set after the defects period ended, say) and there is no practical-completion release to raise after it: the final claims everything still held, that share included. Void the final release claim and the share can be released again.
  • Once the final release claim is raised, the practical-completion share is never offered again — not even when the final was edited down below what is held, or a later claim held more retention. Whatever is held beyond the final claim is final-balance money. Release retention offers it as The rest still held, and drafts a second final release claim for exactly that amount, beside the first. That works even when the client has paid the first final or it is in Xero, where it cannot be voided. Until the rest is sent the job cannot close, because that retention is still outstanding.
  • Recording the outcome does not change the rate book. Feeding actuals does, and only what you tick.
  • Both margins on an outcome are margins on the price, wherever it is recorded. Record Project Outcome on Job Costs stored the quote's mark-up as the quoted margin until 17 October 2026; those outcomes were left as they were, so their quoted margin reads higher.
  • Recording the outcome on this page never closes the job, even a settled one; Close project does. Asked through the assistant, recording the outcome also closes a job that is settled with nothing open.
  • Generating the PC certificate again files a new document and links that one. The earlier certificate, and any signature request already out on it, stays in Documents.
  • The actuals feed proposes a unit rate only where a line has a quantity, a real unit and a cost code no other priced line shares. Everything else is summarised per section, in percentages.
  • Closing past open defects is the one override, and your reason is on the record.
  • The review request asks the first client contact who can still open the job; the task names the others. A second pack sent does not ask again, even if the first task was dismissed. Reviews stay with you and are never posted anywhere. They show on the job's Client page.
  • A client contact who has already reviewed the job is never asked again, and one request is open at a time. While a drafted request has not been sent, no other is drafted. The handover request is the first ask, so it is not drafted while any request is open, sent or not. A request that was sent and is still waiting on the client gives way at the end of the defects period, or when someone presses Ask for a review: its task closes as done and the new one takes its place. A review closes every request still open on the job.
  • The end-of-defects-period request comes from the defects period ending on the closeout. A job settled before that date gets no second request; use Ask for a review on the Client page.
  • A warranty a trade sends is collected on the checklist but is not on the warranty register, which the client can see, until you add it. What a trade says it covers is read by you first.
  • A trade can also send documents nobody asked for, up to 20 per job, as warranties, manuals, certificates or as-builts. They arrive collected on the checklist like the rest. A trade cannot replace a document you already hold.
  • Asking a trade does not give them your Base portal. Awarding a trade and emailing them a purchase order share it with the address the email goes to; a trade you engaged by hand may have nobody in it. Until someone there has it, the request waits on your side only, so share it from their page or tell them yourself.
  • The PC email only switches the handover section on for a job where nobody has set it. If someone switched Handover pack & warranties off on the job's Client page, it stays off and the email leaves the pack out.
  • The PC email never gives a client contact back a job you took them off. Someone you took off the job, or whose access you removed on the job's Client → Portal, gets no email.