In this guide

A job's dashboard and tasks

Where a job is up to, and the checklist of what to do next.

What it is

Two screens that answer "how is this job going and what do I do next". The Dashboard is the one-page snapshot of a job: a pane at the top led by the contract sum, with margin, open tasks and open defects beside it, the job's estimate lines, documents, purchase orders and variations counted above them and the next task under them, then the job's details, the next tasks, what the assistant has done recently, who is on site now, the site on a map, the job's money in a sentence, and the latest emails and texts. For the people on the job's team it also holds Decide: the job's money decisions waiting for a person, such as a claim Base drafted for unbilled work. Tasks is the job's running checklist, kept as a board the assistant and your team maintain together, with the PM Agent's plan for the coming week at the top. Both are for whoever runs the job. Neither needs a module switched on.

Under the job selector, the Next: … row opens the Project guide. On a wide screen it stays beside the project content and chat, with no backdrop covering your work. It stays open as you change project pages or ask Base, and remembers your choice for that project. Press the Next row again or the cross to close it. On a narrow screen it opens as a side panel that you can close when you need the page.

The pre-quote checklist follows Run the estimate → Review and approve items → Build and settle scope → Get trade prices → Carry chosen costs and finalise the estimate → Quote/signatures → Win the job. Steps update from real records. A returned RFQ price is not automatically a cost carried in your estimate: choose Use this quote in estimate on the reply you want. On an already-won job, the pre-contract stages are closed and the guide points to the remaining setup and delivery work. At the end of the job, Close it out follows Declare practical completion → Close out the defects → Issue the handover pack → Issue the final claim → Release the retention → Record how the job went → Close the job. The final claim and retention steps are judged once practical completion is declared.

The next unfinished step has Take me there, Walk me through and, where Base can help, Ask Base for help. You can also ask “What should I do next?” in chat. Base receives the same project checklist and can guide you through the next step from where this job is up to. Approving items, carrying costs, awarding work and sending documents remain your decisions.

Two prompts can sit at the top of every page of a job, not only the dashboard. Quote signed — it's official. appears when the client has signed one of your quotes and the job is not won yet, or when they have signed and your countersignature is waiting. This job isn't in your CRM yet — add it? appears when the job has no lead.

Before you start

  • A project exists. The dashboard shows zeroes rather than errors on a brand-new job.
  • The money card and the Margin tile need Job Costs, Cashflow or Claims on for you; without any of them the card does not appear and the tile shows the quoted margin. Only Cashflow brings the company-wide figures (the bank balance from Xero, GST, runway, profit) along with the job's; Job Costs or Claims alone show this job's line and what is waiting on it.
  • Decide shows for people with Cashflow, and for people on the job's team (named on its Team page) who have Job Costs, Invoices or Subcontractors. Each sees only the kinds of decision their own modules cover: a claim needs Invoices, an order Subcontractors, a subcontractor claim Job Costs.
  • Tasks need nothing else. The task review is not switched on when a job is created: Base offers it once the job's estimate is finished, or you can turn it on yourself under Keeps this list up to date → Schedule.
  • The task review and the PM Agent are part of the Automations module. Without it, one plain line takes their place on the Tasks page and your tasks work as normal.
  • Turning them on, changing the schedule and Review now need Automations → Install, or being the job's head PM (named on its Team page): the head PM can switch them on or off for their own job without Install. Anyone else who can see them reads a line saying who can switch them.
  • The PM Agent is set up once for the whole business, by someone with Automations → Install turning it on for a job. Until then, or while it is paused for the business, a head PM without Install can't turn it on and is told who can. They can still switch the task review.
  • The signed-quote banner shows for people with the Documents module. Marking the job won from it needs Projects → Edit.
  • Adding the job to the CRM in one click needs CRM → Edit. Without it the question is never asked, and Create the lead for me in the guide says the lead could not be added.

How to

Read the dashboard

  1. Open the job's Dashboard. The bar at the top is Base's line for this job: a dot that pulses only while Base is working on it, what it is doing (or last did), N done this week and N to decide; press it for Now, Next and Watching. Anything that could not wait for the standup sits under it in a red box with its action. The chat beside the page carries Base's notes on the job in a drawer on its edge. Under it, the This job pane leads with the Contract sum (ex GST); beside it are Margin, Open tasks (with how many are high or urgent) and Open defects, red while any are open. The line above them counts the job's estimate lines, documents, purchase orders and variations, and Programme and Scope sit on its right. Every figure opens the page it counts. Next under the figures is the most urgent open task; press it for the job's Tasks.
  2. The Margin figure reads the job's forecast margin from the finance position and says how it moved; with no position yet it shows the quoted margin and says so.
  3. Next up lists the six highest-priority open tasks. A task that carries a suggested prompt has a Run button that opens a new chat thread with that prompt and closes the task out when the assistant finishes.
  4. On site now lists everyone with an open sign-in, with how long they have been there; Roll call opens Site home.
  5. Location places the site on a map from the address (it geocodes the address the first time) and links to Google Maps.
  6. Money gives the job's position in a sentence and lists anything waiting on this job, each with a link to act on it. Recent comms shows the last five emails and texts; All comms opens the job's Comms page.

Mark the job won when the client has signed

  1. When the client has signed one of your quotes and the job is still being quoted, every page of the job shows Quote signed — it's official., saying who signed which quote and when.
  2. Press Mark job won. It opens the same Mark won window as the dashboard and the estimate: check the contract sum (ex GST) and the terms, then win the job (see The estimate). Once it is won the banner goes.
  3. Open signed quote shows the signed copy. Remind me later hides the banner in this browser tab until you close it; it comes back next time while the job is still not won.
  4. Without permission to change the job's status, the banner says to ask whoever runs the job, and has no Mark job won.

Upload the signed contract on a won job

  1. A live won job with no signed contract on file (won with Win without it, won before the signed-paperwork rule, or its contract deleted) shows Signed contract missing — upload it. on every page.
  2. Press Upload it, choose Signed contract or Signed quote, acceptance or PO, and upload the PDF or photo, or press This is the signed one beside a document already on the job. The line goes once Base has it.

Countersign a quote the client has signed

  1. When the client has signed and your business's signature is still to come, every page of the job shows The client has signed — your signature is the last one.
  2. Press Sign now. Your signing page opens in a new tab; see Signing a document. Everyone is emailed the signed copy once you have signed.
  3. When the signature it waits on is a teammate's, the banner names them and has no Sign now.

Add the job to the CRM

  1. On a job with no lead, the guide's Track it in the CRM step offers Create the lead for me, and pages of a job being quoted or under way ask This job isn't in your CRM yet — add it?
  2. Press Create the lead for me or Yes, add it. Base makes the lead from the job's client, contacts, site and value, at the stage the job is at, and links it to the job. It says Added — open in CRM, and lists anything it could not fill in for you to add on the lead.
  3. To check the details first, press Open the form in the guide instead: the new-lead form opens filled in from the job. Not now hides the question in this browser tab until you close it.

Assign subcontractors and crew once the job is won

The site sign-in shows each person the work of their trade from the programme, and the diary and timesheets record who did what. Both depend on the people on the job each having a trade.

  1. Open Where this job is up to. Under Set it up, Assign subcontractors and crew says what is missing: the trades on the programme nobody does yet, or how many people on the job have no trade.
  2. Press the step (or Take me there when it is next). It opens the job's Subcontractors page, or the Crew Roster when all that is missing is a worker's trade. Engage a subcontractor for each trade, with the trade filled in.
  3. Add your own people under Expected crew on the job's Crew & Timesheets tab. A worker's trade is set on their page in the Crew Roster.
  4. Ask Base for help has the assistant list the trades with nobody, who in your contacts or crew could do them, and who has no trade. It engages nobody until you say so.

The step ticks itself once every trade with programme work starting in the next three weeks, or already under way, has a subcontractor or crew member of that trade on the job, and nobody on the job is without a trade. With no programme yet, it ticks once someone is on the job and everyone has a trade.

Name the head PM

The head PM runs the job. The job's notices, its kick-off tasks and the assistant's automatic runs go to them. With nobody named they go to the admins, and a project manager who is not an admin hears nothing.

  1. Open Where this job is up to. Under Set it up, Name the head PM says who it is, or "nobody named".
  2. Press the step. It opens the job's Team page. Link a team the person is in, then add them as Head PM. If they are not in a team yet, add them to one on Teams first: a person joins a job only through a team linked to it.
  3. Or name them in the Mark won window when you win the job (see The estimate).
  4. Ask Base for help has the assistant list the people in your teams, then link the team and add the one you pick. It does not pick for you.

Switch a job in or out of practice

  1. Under Project details, find Practice. Only an admin (or the account owner) can flip it; everyone else sees whether the job is a practice job or a real one.
  2. Flip it. A window says what changes: a real job's claims, bills and orders count in your money figures and can be sent to Xero, including anything already on it; a practice job leaves your money figures and nothing more from it is sent to Xero, while anything already in Xero stays there.
  3. Confirm. Base records who switched it and when. See Projects for what a practice job is.

Add a task

  1. Open Tasks. Type into Add a task to the backlog… and press Add (or Enter).
  2. The task lands in the Backlog column. From its card you can start it, mark it done, dismiss it, delete it, or reassign it.

See the job's meetings and book the next one

  1. On the Meetings tab of the job's Tasks page are the job's next meetings: when, the kind, how many are coming and how many from outside, and a clash flag when someone on it has something else on. Press one to open it.
  2. A Suggested line is a meeting the job's stage should have and has not booked yet — the client site visit while quoting, the pre-start once it is won (see Meeting settings). Press Schedule to open it pre-filled, pick the time and press Send invites. Nothing is booked by itself.
  3. Arrange a meeting books anything else on this job. Every meeting is also on the Calendar.

Record a meeting's minutes and its actions

  1. On the Meetings tab of the job's Tasks page, press Add minutes.
  2. Drop the minutes on the form (a PDF, a document or a photo of them), or click to choose them. Base reads the meeting, the date, who came, the decisions and each action with who has it and when it is due, and shows them beside the file. Or type them in.
  3. Check the values, fix any action that was misread, and press Confirm and save (Save when typed in).
  4. The minutes go into the notes of that day's meeting on this job, or the meeting is recorded if it was never booked in Base. Each action becomes a task on this page for the person named. An action whose person Base does not know goes to the job's head PM, with the name in the task.

Work the board

  1. The three columns are Backlog (to do), Active (in progress, blocked or waiting) and Finished (done or dismissed). Finished tasks move to the Archive two days after they close; Show archive lists them, where they can be reopened or deleted permanently.
  2. The status button on a card steps it along: Start, Mark done, Reopen, Resume. Statuses are To do, In progress, Blocked, Waiting, Done and Dismissed.
  3. The owner chip (You, a first name, Base or Unassigned) opens a menu: pick a team member, the team's pool, or Base to hand the task to the assistant. When Base cannot take it (work on site, an approval, a signature) the menu says why and Base cannot be picked. A card marked DECISION is a call only a person can make.
  4. Hovering a card reveals the bell (Set an AI reminder: pick a date and time, press Set reminder), the lightning bolt (Add an event trigger: pick an event type; the assistant re-checks the task when that event fires on this job) and the chat icon (Open the chat this task came from).
  5. A task that carries a draft email or text shows a snippet; click it to read the full draft, edit the subject and body, and Approve & send or discard it. Nothing is sent until you approve.
  6. Group by: Area of the job sorts each column into the areas of the job — Estimate, Scope, Tenders, Drawings & RFIs, Contracts & documents, Variations, Programme, Subcontractors, Purchase orders, Site, Defects & handover, Money and Comms — with a count beside each. An area's name opens that page of the job (Tenders opens the job's tenders). Nothing puts the columns back to one list. Base remembers your choice on this computer.
  7. Press a card's title to open the task. It is the same task as on Tasks: besides status, owner and dates you can give it a team, the day it is planned for, a repeat, a checklist, sub-tasks, files, followers and comments with @name.

See the job's plans

  1. Press the Plans tab (next to Board). Each of this job's plans — a goal with a few steps that depend on each other, made by Base's project manager or by you — is a card with its steps in order, each with its owner and whether it is done, ready, being worked by Base, or waiting on an earlier step. Tasks not in a plan sit under Not in a plan.
  2. The chips On me, On Base, On my team and Waiting narrow the cards. Press a step to open it beside the list: why it is there, what it needs first and what it unblocks, who does it, and Mark done, Approve (a decision) or Give to Base. It is the same step as on Tasks → Plans; marking it done lights the next step for its owner.
  3. Board puts the columns back. The page remembers which you chose on this computer, and the open tab is in the page's link.

Read the top of the page

The panel at the top counts what is on the board (to do, in progress, overdue, drafts waiting for you) and holds the two automations that work it, each with a light that says whether it is on:

  • Keeps this list up to date (Task review) reads the job and adds, updates and closes tasks.
  • Plans the week ahead (PM Agent) turns the programme into a day-by-day plan for the next seven days.

Both work this job only, and they share one switch: the task review's schedule. Turning on the PM Agent turns on the task review too, and switching the review off stops both.

Change how often the list is reviewed

  1. In Keeps this list up to date, press Schedule.
  2. Pick How often (Every weekday, Every day, Weekly (Mondays), or Off) and a time. Press Save. Off means nothing automatic works this job until you press Review now.
  3. Review now runs a review straight away. New and updated tasks appear on the board as it works, usually inside a minute.

Run the week

The programme's This week button lands here, and My Tasks → Week shows the same plans for every job at once.

  1. The first time, press Turn on in Plans the week ahead. It turns on for this job only, with the task review every weekday at 6:30am. It runs daily programme checks, chases sub bookings, proposes replans and plans the job a week ahead; its morning briefs land in the job's inbox. Plan now runs it again whenever you like.
  2. Once it has run, the This week tab shows the plan. Your next tasks — in this order lists your items, ready ones first; press Done on one to tick it off. Below, each day shows its goal and its items.
  3. The owner chip on an item is a menu: hand it to a team member, Anyone or the PM Agent. The agent keeps your choice when it rebuilds the plan.
  4. Fold days folds the day columns down to their goals; the page remembers it.
  5. Missed tasks appears when the Friday review found committed work that was not finished. Open it and name the business that held each one up so it counts on their record.
  6. Who was booked on site appears once a trade has been booked for a day. Open it to excuse a day that should not count against them, such as when the site was shut.

Decide on this job

  1. Open the job's Dashboard. Decide sits under the job's details and lists what waits on this job: each row says what it is (for example Draft a progress claim), the amount, who proposed it and when, and the evidence behind it.
  2. Type a Reason if you want one, then press Approve. Base runs it as you, exactly as if you had done it on the page it belongs to; the row says Done. and drops off the list, or Could not: with the reason and stays so it can be decided again. Press Reject to stop it; Base does not propose the same thing again for a fortnight.
  3. A row you cannot decide shows why instead of the buttons, and who to ask: the permission you are missing on Team Modules, or that it is over your approval limit.
  4. A drafted claim, once approved, waits on the job's Invoicing tab to be finished and sent.

What happens on its own

  • On the schedule you set, the assistant reads the whole job and works out where it is (quoting, won and being set up, ready for site, on site, or in defects and close-out). It then goes through every area — the estimate and its approvals, the scope, tenders out and quotes back, drawings and open RFIs, the quote, contract, schedule of values and budget, variations, the programme against today, which trades are engaged and when they start, purchase orders, induction, SWMS and the site diary, defects and the close-out checklist, claims and costs, and emails waiting for an answer — and compares it with what that stage should have. It reconciles the board against what is missing or late: it adds what is missing, completes what is resolved and never duplicates an open task. Every task it adds has a due date and sits in its area of the job. It never changes or closes a task you made or have worked on; it leaves its suggestion as a note on the task instead. Giving one of its tasks to Base is not working on it, so it can still update or close a task it added that you handed to Base; renaming a task, changing its details, ticking a step, a comment, a new date or owner, or changing its status yourself all count. Its tasks in the job's Scope area close themselves when the job's scope of works is approved, with a line on each saying so. A task it added that you dismissed is not added again for a month. It posts to the job's inbox only when it changed something. A brand-new job's first review is queued automatically, so empty columns mean the assistant is working, not that there is nothing to do.
  • Once a job is won, Base checks its programme every working afternoon. When site or workshop work in the next two weeks has nobody to do it (a subcontractor's task with no company, or our own work with nobody of that trade on the job), it keeps one task, Assign people to the site work coming up, in the Subcontractors area. It has a checklist line per trade and is due three working days before the first of that work starts. A line ticks itself when someone is down for the trade, your own ticks stay, and the task closes when every line is ticked. Close it yourself and, for a week, it comes back only for a trade it did not list. The assistant's own review sees this task and does not add another for the same trade.
  • Winning a job the first time adds its kick-off tasks, whichever way it was won (Mark won, the client accepting in the portal, an e-signature, the CRM). Name the head PM is added only when nobody runs the job, is due in two days and closes itself when someone is made head PM. Book the pre-start meeting is added only before the job's start date, is due five days before it (a week from the win when there is no start date), goes to the head PM, and you tick it off once it is booked. A job won straight to In progress is on site already, so it gets no pre-start task. Each is added once per job: a closed one never comes back. A job that goes on hold or into the archive and comes back gets none, and neither does one won straight to Completed.
  • A won job moves from Pre-construction to In progress by itself, on the first day someone signs in on its site or on the day its first site work starts on the programme, whichever comes first. The job's header shows where it is up to beside its status: Setting up, Ready for site, On site, or Handover & DLP once practical completion is declared.
  • When the job's practical completion milestone passes, or all its site work is ticked done, the head PM and admins are told practical completion is due, with a link to Handover.
  • Automatic runs on this job act for the job's head PM when it has one, so their briefs and drafts land in the head PM's inbox, not the inbox of whoever turned the automation on.
  • A task assigned to the AI is picked up and attempted with the same tools the chat has. It reports back as done, as waiting with something for you to approve, or as blocked with what it needs.
  • When a reminder fires the assistant re-reads the job first: it marks the task done if it resolved itself, bumps the priority if it became urgent, otherwise sends one short nudge in chat.
  • The dashboard refreshes itself when the assistant changes the job, its tasks, orders, documents or defects from chat.
  • Drafts the assistant writes wait on the task. It never sends an email or text from a background run.
  • With the PM Agent on, it rebuilds the week at 6:45am on weekdays from the programme. Ticking an item done frees whatever was waiting on it, and an item handed to the agent starts on its own.
  • The week is made of the job's own tasks. Putting a task in the week gives it a day to be done and leaves its due date alone. A new task is added only for work no task covers yet. When the week is rebuilt, tasks it drops lose their day but stay on the list. The exception is a task the old week added that nobody started, changed or noted, which is dismissed.
  • When finished work goes unbilled, Base drafts the claim and tells the job's head PM; the notice opens Decide on this page.
  • Quote the client in the guide ticks once one of your quotes has gone out: sent, out for signature, signed, or a quote sent from the job's lead. Its note says how far it got, such as "quote signed 19 Oct", "quote out for signature since 12 Oct" or "2 quotes sent". A quote that came in from a subcontractor or supplier never ticks it.
  • Have the signed quote on file ticks once the client's signature is on the job, however it arrived: the quote signed through Request signatures, or a signed quote, letter of acceptance or client purchase order dropped into the job's Documents or brought in from an email (filed as the client's acceptance). A quote that is only out for signature does not tick it.
  • The signed-quote banner checks again every minute while the page is open, so it appears soon after the client signs and goes once the job is won or you have countersigned.

Things that surprise people

  • The dashboard's money comes from the budget. A job with no budget lines shows zeroes, which reads like nothing has been spent.
  • The Margin figure falls back to the quoted margin when the finance position has nothing for the job yet; the line under it says which it is showing.
  • A card's last line is the latest thing that happened to the task. A status change reads in the board's words (To do → Dismissed); something Base did reads as one short sentence of what it did. The whole record, Base's working included, is in the task's activity: press the line.
  • Decide is not there for someone who is not on the job's Team page and has no Cashflow, even if they run the job day to day. Name them on the Team page. Approving here still keeps to their approval limit, and a decision over it goes to someone whose limit covers it.
  • The task review adds nothing for an area the job is not ready for: no purchase orders or subcontractor bookings before the job is won, no claims before there is anything to claim. A trade is raised for booking about three weeks before it starts on the programme.
  • Dismissed is not deleted. A dismissed task is kept for the record and archives after two days like a done one; Delete permanently is the only thing that removes it.
  • The task review runs at most once a day. A review set to every few hours before 14 October now runs daily.
  • Your plan sets how many jobs can have automation on at once: Trade and Estimator 3, Builder 5, Automater 10. Turning it on for one more job is refused with that reason; switch it off on a job that no longer needs it, or choose which jobs keep theirs under Automations.
  • A job's head PM can switch its task review and PM Agent on or off, and press Review now, even without Automations → Install, for that job only. Your plan's limit and your business's AI allowance still apply, and the tile says "You're this job's head PM, so this switch is yours". In chat the same holds when they ask for their own job, even if an admin has switched the assistant's Install off for them.
  • A head PM turning on the PM Agent turns it on for their job only and leaves the business's PM Agent settings exactly as they are. If someone paused part of it, it stays paused.
  • A job nobody has opened for a fortnight is flagged, then paused a fortnight later. A paused job's task review, PM Agent and event reviews all stop together, and its schedule shows Paused by Base.
  • Where this job is up to is ticked from records, not from anyone saying a step is done. A step stays unticked until the thing it describes exists in Base.
  • Assign subcontractors and crew matches trades by meaning, not spelling: a "sparky" covers "Electrical services". Programme tasks for general work (site establishment, labour, supervision) and tasks with no trade are not counted, and neither are orders, shop drawings, milestones or the council's and client's tasks: only work someone does on site or in the workshop. A subcontractor still only invited is not on the job yet.
  • Issue the purchase orders is a separate step. Engaging a subcontractor says who does the work; the purchase order is what commits the money.
  • A quote the client signs after you sent it with Send quote wins the job by itself, so it never needs the banner. The banner is for a quote of yours they signed some other way, such as one sent for signature from Documents. A subcontractor's quote you signed never raises it.
  • The banner never marks the job won by itself. Winning stays a person pressing Mark won, because it locks the estimate and builds the budget.
  • A lead made with one click on a job that is already won is made at Won, with no follow-up call. On a job still being quoted it is made at Quote submitted, with a follow-up call a week out as the form would set.
  • The CRM question is not asked on a completed, on-hold, archived or sandbox job. On a completed or on-hold job the guide's Create the lead for me still works.
  • Site home for the roll call the dashboard links to.
  • My tasks for the tasks assigned to you across every job, and the Week view of every job's plan.
  • Programme for the schedule the week is planned from.

The Build it section also tracks the build programme. Its completion percentage uses recorded task progress weighted by duration, rather than time elapsed. The programme step stays open until every active task and milestone is complete, so recording a shift or cost alone cannot finish the build checklist. Cancelled tasks are excluded. No programme, or an unavailable programme, is never treated as complete.