In this guide
Safety
Incidents, SWMS and safety paperwork on a job.
What it is
What workers reported from site, and whether anybody went to it; the job's compliance registers as controlled documents; the forms asked at the gate; the SWMS and other safety paperwork on file; and which subcontractors have supplied their SWMS. The page leads with the reports nobody has been to, because a notification that was missed is indistinguishable from an incident that never happened, and "what did you do when it was reported" is the question that gets asked afterwards.
Before you start
- Nothing to switch on; the page is on every job. The Gate forms section is the Forms module's: without Forms it says so in place of the list.
- Reports come from the site QR: workers raise an incident or an issue when they sign out. The QR needs to be at the gate (see Crew and timesheets on a job).
- Gate forms and registers are set up when a job is won and goes to site; a job that predates them has a Set up registers button.
How to
Deal with what was reported
- The line under the page title says how many reports nobody has been to; open ones carry a red edge. Reported from site lists every one, open first: an incident or an issue raised, who reported it, the date and how many photos. Under an incident is what the worker said it was (for example Injury · major), who was involved and what was done straight away, when they answered.
- On an open one, press Mark as dealt with. Write what was done about it (optional, but it is the bit that matters later). If the worker did not say what kind it was or how bad, you can choose those too. Press Record.
- The report shows seen with the date, your note underneath, and drops out of the count.
Report an incident from the office
- Press Report incident beside the page title.
- Drop the incident report or a photo of it on the form, or click to choose it, and Base reads when and where it happened, what kind it was, who was involved, what happened, what was done and whether it is notifiable. Or type it in.
- Check the values and press Confirm and save (Save when typed in). It is listed under Reported from site as an incident, with your name as the reporter, ready to be marked dealt with like any other.
Add a subcontractor's SWMS or insurance
Press Add a SWMS or insurance, drop the document on the form, check the subcontractor, the type and the expiry date, and save. A SWMS is kept for this job; insurance and licences are kept on the subcontractor in Contacts for every job, and Base reminds you before they run out.
Make a defect from a report
- On a report, press Make a defect. An open defect is logged from what was reported: the description, how bad, the day, and the report's photos as its before photos.
- Press Defect logged · open to open it on Defects and assign the trade, the subcontractor and the due date.
- A report makes one defect. Pressing it again on another screen opens the same one.
Draft a notice of delay from a report
- On a report, press Notice of delay. The notice opens saying a site incident occurred on the report's date (or that an issue was raised on site, for an issue raised at sign-in or sign-out). Nothing else from the report is copied in.
- Write what happened in your own words, then add who it goes to, the cause, the time you are claiming and what you are doing about it, check it and save it. Sending it is up to you.
- Once saved, the report shows Notice filed.
Keep the registers
- Registers lists the Site sign-in register, Induction register, SWMS register and Incident register, each with its current revision and status.
- PDF downloads the current revision. Regenerate now produces a new revision from the site record; if nothing it records has changed, it says so and offers to produce one anyway. Finalise locks the current revision so it can no longer be changed or deleted.
- Earlier revisions are listed under each register, kept exactly as issued, each with its own PDF.
Set what the gate asks
- Gate forms says whether the gate asks anything on this job (on by itself when the job is won and goes to site, or by hand) and lists the forms asked at sign-in: the daily pre-start and fit-for-work, a visitor declaration, a sign-out form.
- A job follows the company defaults (edited under Forms) until you press Customise for this project, which copies them here to change. Add a form from the templates: pick it from Add a form, choose who is asked (crew, subbies, visitors), when, and Required or Optional, then press Add. Go back to the organisation defaults drops the job's own list.
- Switch off, in the section's header, stops the gate asking anything on this job.
Read the paperwork
Paperwork on file, at the bottom of the page, has two lists: Safety documents, the SWMS, incident reports and toolbox talks filed on the job, and Subcontractor SWMS, each sub's SWMS with its expiry, red when expired.
What happens on its own
- Registers update at the end of each site day; the incident register within the hour. Never on every sign-in.
- Subcontractors are asked for their SWMS when a trade is awarded; what they upload lands here.
- Your own crew sign on to your SWMS at the site QR: each SWMS filed on the job that is Final or Sent, once per person per SWMS, and again when a new one is filed. Their sign-ons go on the SWMS register beside the subcontractors' workers.
- Documents the assistant generates (ask it for a SWMS, an incident report or a toolbox talk) file here automatically.
- A worker who declares not fit for work at the gate is still let in; the shift records it and the supervisor is told.
- An incident nobody has marked dealt with two days after it was reported gets an inbox item to the job's site supervisor (else the head PM, else the admins), then another once a week until it is marked dealt with.
- An incident reported from the office tells the site supervisor the same way one from the site QR does.
- With Text the person who reported an incident when it is dealt with switched on (Automations → Library → Site supervisor, off until you turn it on, because texts cost money), marking a report dealt with texts whoever reported it — on the mobile they signed in with — that it was looked at and by whom. Your note stays in the register; it is not in the text.
Things that surprise people
- An incident used to produce one notification and nothing that outlived it. Marking it dealt with, with a note, is what makes the record. Until then Base keeps reminding the site supervisor.
- Finalising a register locks that revision only. The next regeneration makes a new one; the finalised one is kept as issued.
- What each section is for is written at its foot, under its list, not above it.
- A sub with no SWMS on file is flagged at the gate when their workers sign in; this page is where you see who still owes one.
- A hazard or incident reported at a workshop or office QR is not here: it has no job. It is on Sign-in Locations, where it is marked dealt with.
- A SWMS left as a draft is not asked of your crew, and one that arrived as an email attachment is not either (it is most likely someone else's). Any other SWMS uploaded to the job's Documents is, even a subcontractor's you uploaded by hand.
- What the worker said an incident was stays as they said it. Marking it dealt with can only fill in what they left blank; if you disagree, say so in your note.
- The incident register prints the kind and how bad before the description, for the incidents that say.
- A notice of delay made from a report leaves out what the report says: its words, the kind of incident, how bad it was, who reported it, who was involved and what was done. A notice goes to the client and becomes part of the contract record, and injury details do not belong in it. You write what happened yourself.
- Make a defect and Notice of delay show only to someone who can raise defects or make documents. A defect made here is never shown to the client until someone ticks Show to client on it.
Related
- Forms for the company's default gate forms and incident form.
- Site diary for where the day's safety notes are recorded.