Programme
The construction programme: phases, tasks, dependencies, progress.
What it is
The build schedule for a job: tasks grouped by phase, each with a trade, dates, a status, who is responsible and what it depends on, drawn as a Gantt chart with a list view beside it. It is what the lookahead, the subbie bookings and every slippage warning are measured against. The project manager owns it; the site supervisor runs the week from it.
Before you start
- The Programme module is on (Settings → Team Modules). Without it the tab is hidden, opening its address says Programme is not switched on for you, and the "This week" panel on the job's Tasks page does not appear.
- Changing tasks, importing them from the estimate and reassigning the week's items need Programme → Edit. Bringing the prelims in line with the programme changes estimate quantities, so it needs Estimating → Edit too.
- A job exists. To draft a programme from the estimate or import tasks from it, the estimate has lines.
- To assign tasks to people, the people are on the job's roster (A job's team).
How to
Add a task by hand
- Press Add Task.
- Give it a name, a phase, a trade and who is Responsible; set a duration or start and end dates; tick Critical Path, long lead or milestone if they apply.
- Save. The task appears on the chart in its phase. Open any task to edit it: status and completion, a Delay / Block Reason with its cause and who held it up, the schedule, the assignee and collaborators, its predecessors (Add predecessor — search by name, trade or phase…) and notes.
Build the programme from the estimate
Three routes, from fastest to most considered:
- Import opens Import from Estimate. Tick the estimate lines to bring in (or Select All). Imported tasks arrive with durations but no dates; the page offers an AI sequence to date and link them.
- Quick Plan (under the … menu) builds a template programme between a start and finish date you give it, with the critical path and long-lead items marked and predecessors pre-linked, scaling durations to fit.
- AI Plan opens a chat thread in programme mode. The assistant reads the live programme and improves, replaces or creates one from the estimate scope and the engaged subcontractors, with durations, dependencies, critical path, long-lead flags and milestones, anchored to the job's start and handover dates. It shows you the plan before writing it.
Lock a baseline
- Press Lock Baseline (or Re-lock Baseline if one exists). The confirmation explains that every task's current start and end dates are captured as the baseline, and that re-locking overwrites the previous one, which is not kept.
- Confirm. The chart overlays the baseline under each bar, the At Risk card becomes Slipped (tasks past their baseline finish), and the daily check can now report drift.
Work the chart
- The canvas has two tabs: Gantt (the timeline, with Day, Week and Month scales and Fit to see the whole programme) and Tasks. Between them, This week goes to the PM Agent's seven-day plan on the job's Tasks page. Add and AI Plan lead the toolbar.
- The chart opens on today. When nothing is on the programme around today (the work starts later, or there is a gap), it opens on the next task instead, so the first thing you see is a bar. Jump to today in the side panel brings today back.
- Drag a bar to move a task. The Linked tasks when you drag control decides what happens to the tasks that depend on it: ask each time, shift them together, or keep their dates. A red ring on a bar means it starts before its predecessor ends; a task's row can spotlight its predecessors and successors.
- The health cards at the top count completion, tasks, delayed or slipped work and critical-path tasks, with the handover date and whether it is overdue.
- Where the page lists procurement deadlines or sequence clashes, Send to the programme agent hands every issue to the assistant to validate and restructure, keeping the handover date fixed unless it cannot.
Add a hold point to a task
A hold point is an inspection the task waits for. Open the task, then under Hold points press Add a hold point, say what is inspected and by whom, set Needed by if it is earlier than the task's start, and press Add hold point. The task is not ready until it is passed. Recording it passed, waiving it or linking its ITP is on the job's Hold points page. In the list view, a task with a hold point not cleared shows a clipboard mark beside its name.
Mark a milestone as an inspection
Open a milestone, tick Inspection (hold point gate) under Attributes and save. It is then listed as an inspection on the job's Hold points page, on Site home and in the afternoon notice when it is due.
Move practical completion for time a variation granted
- On Variations, press Move practical completion on an approved variation that granted time. This page opens with the practical completion milestone and a note of the variation and the working days it granted.
- Press Move by N working days to move the date on the form, or pick the date yourself. It counts Monday to Friday, so check it against public holidays and shutdowns.
- Press Save. Nothing moves until you do; saving reschedules what follows, as any edit does. Close the panel instead and nothing changes.
Export or print
Under the … menu: Export to Excel and Print programme.
What happens on its own
- When the programme's length disagrees with the prelims priced per week in the estimate, a banner says so and offers Reprice at N weeks. Nothing moves until you press it, and the banner suggests leaving alone a line whose term really is fixed.
- With a baseline locked, the daily check posts a notification when a task drifts past its baseline finish.
- At 6:15am on weekdays Base checks every live job's programme, whether or not the PM Agent is on. It uses fixed rules, no AI.
- A task past its finish date and not marked complete tells the person it is assigned to and the head PM, once in its first three days late and once more a week on.
- Subcontracted work coming inside its booking window (three weeks before it starts, unless you set another) with nobody booked tells the head PM once, and once more a week before it starts if nobody is booked by then.
- A handover buffer going amber or red tells the head PM, at most once a week for each colour.
- A client selection past its need-by date tells the head PM, in its first days late and again a week on. One the client has already chosen on in their portal is not late on their side: it waits for you to confirm their choice, and the check stays quiet about it.
- A hold point (an inspection the work waits for) due by the next working day and not cleared tells the job's site supervisor and head PM, once for that due date, with a link to the job's Hold points page. One still not recorded more than two weeks after it was due is told again once a week until someone records it passed or waives it.
- With no head PM on the job, the admins hear instead. Each notice opens this page, and each can be paused on Automations.
- A selection can be put to the client from the job's Client page, where they choose in their portal. Confirming their choice there clears the selection here, and the task it held up may become ready.
- With the PM Agent on, it runs at 6:45am on weekdays (and whenever you press Plan now on the job's Tasks page), rebuilding the week from this programme and posting a brief. The week itself is on the job's Tasks page and in My Tasks → Week.
- Sub-booking state (requested, tentative, confirmed) from your commitments is read onto the bars, so a bar can say whether the trade behind it is actually coming.
- A task's company is filled in when its trade is awarded or a subcontractor of that trade is engaged on the job: only on tasks nobody holds, never on work you planned to do with your own crew. The task's history says it came from the award. That company is the one asked to confirm before the task starts, and its workers see the work when they sign in on site.
- Issuing a purchase order with Create programme task ticked adds a task for it; completing the order closes that task.
Things that surprise people
- With linked tasks set to shift together, moving one task moves what depends on it. That is the point, but a single drag can shift the handover date. Check the critical path before you save.
- There is nothing to slip against until a baseline is locked. Re-locking throws the previous baseline away.
- A task that is finished on site but not marked complete reads as late. Set its status or completion so the morning check stops counting it.
- The buffer notice needs a locked baseline and a handover date on the job. Without both, nothing is measured and nothing is said.
- Installing a recipe from the Programme watch pack replaces the built-in notice for that alert on the jobs it covers, so you hear it the pack's way, not twice. If a recipe is set to fire on fewer days, the built-in notice still speaks on the others.
- Pausing the morning check on Automations stops these notices only when the PM Agent is off. With the PM Agent on, its own copy of the check takes over. To stop a notice, pause the notice itself.
- A programme that gets longer does not reprice the prelims on its own. The banner offers to; you decide.
- Approving a variation with time never moves the programme by itself. Moving practical completion is always your edit here. If the programme has no practical completion milestone, the page says so and you move the last task by hand.
- A task with an open constraint should not be committed for the week. Committing it anyway is how a plan quietly becomes fiction.
- Quick Plan is a template fitted to your dates. AI Plan reads your estimate and your subbies. They are not the same thing.
Related
- Estimate for the lines the programme is drafted from.
- Subcontractors on a job for the trades the bookings chase.
- A job's dashboard and tasks for the seven-day plan, review misses and site bookings.