Purchase orders

Orders issued to subcontractors and suppliers on a job.

What it is

A purchase order is the formal instruction to a subcontractor or supplier: this scope, this price, these dates. The Purchase Orders tab on a job lists every order with its status, value, what has been billed against it and what is left, and opens each one to show its budget line, bills, variations, prepayments, acceptance, every send and every document. Issuing an order is what makes money committed against a budget line. (Until October 2026 the UI called these work orders.)

Before you start

  • The Subcontractors module is on (Settings → Team Modules). Without it this tab says it is not switched on for you, and the Estimate tab's section menu has no Tender invitation or Issue purchase order.
  • The Billed and Left columns, and the budget line in an opened order, need Job Costs as well. Without it they show a dash and the order's own value only.
  • Orders are issued from the Estimate tab, section by section, so the estimate has sections with lines.
  • The sub or supplier is in Contacts with an email. A sub whose insurance has expired cannot be sent an order.
  • For the Committed column to move, the trade has a budget line on Job Costs.

How to

Issue a purchase order

  1. On the Estimate tab, open a section's menu and choose Issue purchase order. Awarding a tender on the Tenders page opens the same screen with the tendered price and scope already in it.
  2. Step 01: the scope of works. It starts from the lines in the section (or the scope they tendered). Draft … scope asks Base to write the trade's scope when none is written yet; Restore Base draft or Restore tendered scope goes back to it after you have edited. Pick who it is Awarded to, set the value (an awarded price is the price agreed, not the estimate), confirm the dates and attach project documents. The value is measured against the trade's budget line; changing it away from the awarded price or the estimate needs a written reason, recorded against you on the order.
  3. Step 02 Review & send: the email they will receive, the order value and the on-site dates, and What issuing does: the budget line moves from estimated to committed, a programme task is created if ticked, the PDF is generated and filed, and a countersignature can be requested.
  4. Under Their quote, choose the quote they sent from the job's files, or upload it. A new order can't be sent without it; an awarded order already carries the quote they tendered.
  5. Press Issue & send. The order goes to their email, lands on the Purchase Orders tab as Issued, and the budget line shows the committed value. An order cannot go out with an empty scope, no recipient, or expired insurance.

Track an order

  1. Each row shows the PO number, who it went to, type (Purchase Order, Supply & Install or the assignee type), value, Billed and Left (from countable bills only; unapproved bills are shown as held and not counted) and its status.
  2. Change the status from the dropdown: Draft, Issued, Accepted, In Progress, Completed, Cancelled. Moving a draft to Issued, Accepted, In Progress or Completed records it as sent outside Base: nothing is emailed, the value is committed, the issued date is set, and it is recorded on Money → Decide. If the order is over your approval limit it waits there for someone who can approve it. Marking an order Completed posts the value not already covered by linked bills as cost, so the job is charged once; it also closes the order's programme task.
  3. A supply order shows a Delivered control; set the date goods arrived, or clear it.
  4. The row's buttons download the PDF, prepare the order document for review, edit the order (scope, issued and due dates, delivered date, notes) or delete it after a confirmation.

Say where delivered equipment goes

Use this when the job has a floor plan with the equipment or devices on it, so the installer can scan the box and see where it goes.

  1. On a supply order, press Receive….
  2. Under a line, open Goes to… and pick the spot on the plan, for example EQ-01 Combi oven — Kitchen. Choose Goes to… (none) to clear it.
  3. Optionally, pick who installs it in Installed by…. You can choose any company engaged on the job that has an email address.
  4. When the goods arrive, record the receipt. Each item received on that line gets its own equipment label. The installer you named is emailed a link for each item showing where it goes.
  5. Press Print equipment labels and stick a label on each box.

Scanning a label shows a crop of the plan with the spot in red, plus the room, the mounting height, the services the item needs and any install notes. Your crew can press Installed with their crew PIN, as can anyone signed in to Base with Edit on Workshop or Joinery, and the install appears in that day's site diary. See Scanning a label.

Attach the quote to an order

An order is issued or accepted only with the quote it was raised from attached. A draft without one shows no quote on its row.

  1. Click the order's row to open it.
  2. Under Quote, press Attach quote (Attach another for a revised quote).
  3. Upload the quote, or pick it from the files already on the job: a quote sent in chat, an emailed attachment or the file a tenderer submitted.
  4. Press Attach quote. It opens from the order, and from Job Costs beside the order and every bill on it.

Open an order

Click a row. The panel shows what was assigned, notes, the Quote it was raised from, the Budget line (estimated, committed, actual), the drawdown (billed, paid, held, left, over), Variations, Paid ahead, the Order facts (PO number, type, to, contact, terms, cost code, Xero status), the Dates, the Accepted record if the sub accepted, every Sent email and every Document.

Price a subcontractor on day rates, or set their daywork rates

  1. Open the subcontractor's order. In Pricing, choose Lump sum or Day / hourly rates.
  2. Press Add a rate. Pick Hourly, Overtime (hourly), Weekend (hourly) or Day rate and type the rate. On day rates, also give the hours (or days) allowed — that allowance is the order's value.
  3. Press Add.

On a lump sum the rates are what extra work (daywork) is charged at; the order's price does not move. Daywork → opens Timesheets → Daywork for the job, where the hours are priced and approved.

Vary an order

  1. In the open order's Variations panel, add one: the variation, a reason, the amount (negative for a credit) and detail. It is proposed.
  2. Approve files it through Money → Decide as you: the order's value and its budget line move with it. Reject records a reason; Withdraw takes a proposal back and changes nothing.
  3. A subcontractor can also ask for one from their Base portal, once they have accepted the order. Their request is in the same panel, Pending, with Asked for by and their email, and "their quote is in Documents below" when they attached one. Approve or reject it the same way. When you reject it, the reason you type is shown to them in their portal. On Money → Decide the request says the subcontractor asked for it at their own price, with their reason, what they wrote and whether they attached a quote, so nobody approves it there thinking a colleague put it up.

Receive a delivery from the phone app

  1. In the Base Management phone app, open the job and tap Purchase orders (or the purchase orders tile). The list opens on To receive: supplier and supply-and-install orders that have been issued and are not yet in full, each with its value (ex GST) and when it is needed.
  2. Tap the order. Choose the day it arrived (Today, Yesterday or Another day) and type the docket or delivery-note number.
  3. Each line shows what was ordered and what has come in so far, and Receive now starts at what is still outstanding. Change a line to what is on the docket; leave it empty if none of it came. An order with no lines takes the receipt for the order as a whole. An adjustment line (the difference between the agreed price and the lines) is received with the rest and cannot be changed, the same as in Receive… on the web.
  4. This completes the order is on when every line will be in full. Turn it off for a part delivery, or on to close an order that will not be topped up.
  5. Add Notes (damage, short delivery, who signed) and, if you like, a Photo of the docket. The photo is filed in the job's Documents as a delivery docket. Once the receipt is recorded the docket is marked dealt with, so the Documents tab does not offer to record it again.
  6. Press Record receipt. The app says whether the order is now in full, anything received over what was ordered, and any joinery materials marked received. The receipt is listed under Receipts on the phone and on this tab.
  7. If the app says it couldn't record the receipt because the signal dropped, look under Receipts first: it may have gone through. Pressing Record receipt again on the same form never records it twice; the app says Already recorded instead.

Receive a delivery from its docket

  1. On the order, press Receive…, then Read the docket at the top of the form.
  2. Drop the delivery docket (a PDF or a photo) on the form, take a photo of it on a phone, press Say it and read out what arrived, or type it in. Base reads the supplier, the docket number, the day it arrived, each item and its quantity, and who signed for it.
  3. Check the items against the docket. Tick Everything ordered has arrived if it all came, whatever the docket calls it.
  4. Press Confirm and save. Base matches each item to the order's line by its words ("90x45 MGP10 4.8m" is the line "90 x 45 MGP10 pine, 4.8 m lengths") and records the receipt, the same as Receive… line by line. An item that matches no line is kept in the receipt's notes and the form names it; the docket is filed on the job.

If none of the items match a line and the box is not ticked, nothing is recorded: receive it line by line instead.

Record a prepayment

Under Paid ahead, Set it up files one instalment to Money → Decide; split it on the row afterwards. A requested prepayment needs the supplier's invoice or pro-forma attached before it can be paid.

To attach it, press Attach the deposit invoice under Paid ahead (it reads Add deposit invoice when nothing is waiting). Drop the supplier's invoice or pro-forma on the form, check the total and GST, and press Confirm and save.

  • With an instalment waiting, the invoice is attached to it (the one whose amount it matches, else the first waiting), and it can now be approved on Money → Decide. The finance contacts are told.
  • With nothing waiting, a prepayment is requested for the invoice's amount ex GST, with the invoice attached, and it waits on Money → Decide.
  • Typed in with no file, a waiting instalment is left alone and the form asks for the file: approving it waits on the paper.

What happens on its own

  • A client variation approved on the Variations page or in chat adds its share to the affected order in the same step, within the approver's limit. One the client approves in their portal or by signing, or one over the approver's limit, waits on Money → Decide.
  • When a subcontractor asks for a variation in their Base portal, the job's head PM (else your admins) gets a notification, and the request is filed on Money → Decide within the hour. Nothing on the order moves until someone approves it.
  • When you approve or reject a variation a subcontractor asked for, their portal counts your answer until they read it. With Tell a subcontractor their variation request is approved and …is rejected switched on under Automations → Library, they also get it by email, with your reason when you reject it.
  • Replies to the order email come back into the job; an acceptance is recorded on the order with when and how.
  • An issued order the subcontractor or supplier e-signs in Base is accepted, and the Accepted record says "by e-signature" with the time they signed. It is accepted when they sign, without waiting for your own signature on the order. A signed draft is not accepted; whoever sent it for signature is told to issue it. See Signing a document.
  • In their Base portal the subcontractor sees each order with its approved variations (number, title, amount and the day it was approved), the original value they add to, when it is needed, and where it sits on the programme. Below those are the variations they asked for that are not on the order yet, with your reason when you rejected one. The detail you write on a variation is not shown there; they read it only in the amendment notice you choose to send.
  • Bills pulled from Xero or read from receipts that match the order link to it and draw it down; an order is drawn down only by the bills linked to it.
  • An order in Xero shows its Xero PO number on the row; one deleted in Xero is flagged as no longer a commitment.
  • Issuing an order engages the subcontractor on the job if they were not already.
  • On a day-rate order, each week of approved daywork is recorded as received on its rate lines; a bill from the subcontractor approves itself (when your policy allows) only up to the value of hours received and not yet billed.
  • A receipt recorded in the phone app is the same receipt as one recorded here. The receipt that completes an order sets its delivered date, and the job's head PM is told it arrived in full. From then a bill that fits the order and comes from its supplier can approve itself, if your automation policy allows it.

Things that surprise people

  • An order needs its quote attached before it is issued, accepted, started or completed. Changing a draft's status without one says so and changes nothing. An order Xero raised is exempt, and an order committed before 24 October 2026 keeps going but shows that its quote is missing.
  • An order needs its trade and cost code before it is issued, accepted, started or completed. A draft does not. Base works both out from the estimate section, the trade's name, the trade line's cost code or the cost code on its estimate lines. When it cannot, nothing is issued or sent and it says what to pick: one of the job's trades, or a cost code, or set the trade line's code on Job Costs. An order that came in from Xero is never stopped this way.
  • Once issued, the value moves only by a variation. The paper the sub holds and the number in Base stay the same.
  • An order keeps the first acceptance recorded on it. When the sub has already accepted in their portal or by signing, a later email reply saying they accept still comes back into the job, but it does not replace how, when or with what note the order was accepted.
  • A subcontractor sees every variation you have approved on their order in their portal, whether or not you sent them the notice, but not one you have only proposed, and not your description of it.
  • An order on a trade with no budget line still exists, but the Committed column does not move. Create the line on Job Costs first if you want it tracked.
  • Completing an order nets it against the bills already linked to it. If you expect a bill still to come, link it before you complete, or the completion entry will be larger than the final cost.
  • A legacy order carries one value and no lines.
  • Delivered is a date on the order, recorded here. Receiving goods line by line is Receive… beside it, or the phone app.
  • Only supplier and supply-and-install orders that have been issued take a receipt on the phone. A subcontract or a draft opens this tab instead, and undoing a receipt is done here.
  • A receipt is added to what has already arrived. Sending the same Receive… form twice, here or on the phone, records it once; a second delivery of the same goods is a new receipt, recorded after the form is cleared.
  • Recording a receipt needs Subcontractors → Edit. The Site Supervisor preset leaves it out on purpose, because a receipt is the delivery leg of the three-way match; an admin ticks it for a supervisor who should receive goods. Without it the phone says so when you press Record receipt.
  • Paid ahead on an order that takes a deposit is part of Cashflow. Without Cashflow the panel says so instead of listing the instalments.
  • A practice job's purchase order carries PRACTICE — NOT A REAL DOCUMENT across every page, and sending one from a practice job asks you first. The assistant asks you too, and an automation never sends from a practice job.