Hold points

The inspections the work waits for, on the programme, with the signed ITP behind each.

What it is

A hold point is an inspection the work on the job waits for: the engineer at the steel before the pour, the waterproofing certificate before tiling, the council frame inspection before the lining goes on. Each one sits on a task on the job's programme, and that task is not ready until someone records the inspection passed. Hold points in the job's nav lists them for a job: the ones not cleared yet, most pressing first, the inspection milestones on the programme, the ITP and inspection forms filled on the job, and the ones already passed or waived. It is built for a phone on site as much as a desk.

The line under the page title names the next hold point and when it is due. Under it, three figures: how many are not cleared (and how many have work started), how many are due by the next working day, and how many inspection milestones are still to come. Tap a figure to jump to its list. Each list below is its own section, with what it is for written at its foot.

Before you start

  • The Programme module is on for you (Settings → Team Modules). Hold points live on the programme, so without it the page is not in your nav. Changing them needs edit on the Programme.
  • The job has a programme with tasks. A hold point always belongs to a task.
  • To name the ITP to fill, or attach a signed one as the record, the Forms module is on for you and your business has an ITP or inspection form (Forms → the starter library has a Pre-pour ITP and a Footing founding ITP).

How to

Add a hold point

  1. Open Hold points on the job and press Add a hold point at the top of Not cleared. The form opens at the head of that list. (You can also add one from a task on the Programme: open the task, then Add a hold point under Hold points.)
  2. Pick the task it holds from the list (each shows when it starts), say what is inspected and by whom ("Engineer to inspect the slab steel"), and pick a Needed by day if it must be done earlier than the task starts. Left blank, it is due when the task starts.
  3. Pick the ITP to fill if you use one.
  4. Press Add it. The task is now not ready until the hold point is passed, and the hold point shows on Site home and in the afternoon notice when it is due.

Fill the ITP

On a hold point with an ITP, Fill the ITP opens that form on Forms, ready to fill for this job. Submit it there as usual. Submitting it does not pass the hold point.

Act on a signed-ITP suggestion

  1. When an ITP that is signed off is submitted on the job, the site supervisor gets an inbox notice like "Pre-pour ITP signed — pass the Slab pour hold point?".
  2. Open it. When one hold point names that ITP, its Passed… panel is already open with that signed ITP picked. When several do, each of them says the ITP could pass it; pick the right one and press Passed….
  3. Check it is the right pour or area, then press Record it passed. Nothing is passed until you do.

Record a hold point passed

  1. Press Passed… on the hold point.
  2. Pick the signed ITP that passed it. Forms filled on this job are listed with the hold point's own ITP first; only ones marked Signed off can be picked. Certificates and inspections recorded on the job are listed after them (never a failed inspection). Or pick No form — I have the result when the result came another way, such as a certifier's letter.
  3. Press Record it passed. It moves to Passed and waived with who recorded it, when, and the ITP that was the record. If it was the last thing holding the task, the task is ready.

Record a certificate or an inspection

  1. At the top of Certificates and inspections, press Add certificate (a Form 16, an engineer's or a trade's certificate) or Add inspection (an inspection or test, and whether it passed).
  2. Drop the certificate or report on the form, or click to choose it. Base reads the type, who issued it, the number and the date (for an inspection: what was inspected, by whom, the result and what it found) and shows them beside the file. Or type them in.
  3. To pass a hold point with it, pick the hold point under Passes hold point (Hold point on an inspection).
  4. Press Confirm and save. It is listed under Certificates and inspections. A certificate, or an inspection that passed, records the hold point passed with it as the record, the same as Passed… does. A failed inspection, or one passed with conditions, leaves the hold point open.

A certificate with its file also fills the handover checklist's missing compliance certificate, so it is not chased again at handover.

Waive a hold point

Press Waive… and confirm. Use it only when the inspection is no longer needed; it stays in the history as waived, with who and when.

Change a hold point

Press Edit on a hold point that is not cleared yet to change what it says, its needed-by date or its ITP, then Save.

Mark a milestone as an inspection

On the Programme, open a milestone and tick Inspection (hold point gate) under Attributes, then save. It is listed under Inspections on the programme here, and on Site home and in the afternoon notice when it is due.

What happens on its own

  • Every weekday at 6:15am, Base reads each live job's programme. A hold point due by the next working day (Monday, when it is Friday; public holidays are skipped) and not cleared tells the job's site supervisor and its head PM (or the admins when there is no head PM), once for that due date, with a link to this page. If the date moves, they hear again for the new date. This is an inbox notice: no text and no AI, and it is on for every business.

  • A hold point already late is told for up to two weeks. After two weeks late it is told once a week, saying how many days late it is, until someone records it passed or waives it.

  • Hold points due today or the next working day, and ones up to two weeks late, show on the job's Site home and in the afternoon notice to the job's managers. That includes one whose needed-by date falls weeks before its task starts.

  • Nothing clears a hold point by itself. Submitting the ITP does not, and the assistant will not on its own. Ask it to record one passed and it does so for you, with the ITP or a certificate already on the job if you name it.

  • When an ITP or inspection form is submitted on the job with every hold point on it signed off and nothing failed, and a hold point not yet cleared names that form, the job's site supervisor (else the head PM, else the admins) gets one inbox suggestion to record it passed, with a link that opens it with the signed ITP picked. An ITP with a failed item, or one not signed off, sends nothing. This is on for every business; no text and no AI.

  • When the work a hold point holds has started, or it is two days late, and no certificate or inspection is recorded against it, the job's site supervisor and head PM each get one agent item saying nothing is on file. It goes when one is recorded.

  • A failed inspection tells the job's site supervisor and head PM once, with what it found.

  • When a hold point is passed and nothing else holds up its task, whoever runs that work hears it can start: the task's assignee, else the site supervisor, else the head PM. Not the person who recorded the pass, and nobody when other holds are still open or the hold point was waived.

  • A certificate or inspection report that arrives by email is recognised in the job's Documents, and someone is asked to record it if nobody does.

Things that surprise people

  • Recording a certificate against a hold point passes it, because picking the hold point is the decision. Pick it only when the certificate is for that pour or area.
  • A signed ITP does not clear its hold point. Base suggests it to the site supervisor, but someone records the hold point passed, here or by asking the assistant. One Pre-pour ITP could be for any of three pours, so when several hold points name it Base lists them all and never guesses which one it was for.
  • The suggestion only knows about hold points that name the ITP. A hold point added before its ITP was picked gets no suggestion: pick the ITP under Edit.
  • An ITP with a failed item, or with a hold point on it that is not signed off (inspector, date and signature), cannot be the record of a pass.
  • Work started on a hold point means the task it holds is in progress while the hold point is still not cleared. Check it was not a mistake.
  • An old hold point that no longer applies keeps coming back once a week until you waive it. Waive it here and the notices stop.
  • This is not Inspections under Build in the main nav. That workspace is for certifiers assessing lodged plans.
  • Add a hold point is greyed out when the programme has no unfinished tasks: a hold point always holds a task, so add the task on the Programme first.
  • Linking an ITP to a hold point needs a database update your administrator applies. Until then, hold points work without the ITP picker.