In this guide
Portfolio
Every live job's programme on one timeline, and the milestones that have slipped.
What it is
Every live job on one timeline, so you can see where each one is on its programme and which have slipped. Each job is one bar, from its start to its handover, filled to show how much of its programme is done, with its milestones marked as diamonds. Unroll a job and its programme tasks appear on the same timeline as every other job, so you can line them up. It is for whoever runs delivery across several jobs: the owner, a construction manager, the project managers. It used to be the Timeline view on the Tasks screen.
Before you start
- The Portfolio module must be on for you (Settings → Team Modules). It is on unless an admin turned it off for you; anyone who had Programme has it. If it is off, the page says so and offers the dashboard.
- At least one job that is quoting, in pre-construction, awarded or in progress. Completed and archived jobs do not appear.
- A job needs a programme for its bar to fill and its milestones to show. Build one on the job's Programme page, or ask the assistant.
How to
Read the timeline
- Open Portfolio. It is in the Delivery workspace.
- Each row is a job. The figure beside its name is the share of its programme tasks that are complete. A dash means it has no programme tasks with dates yet.
- The bar runs from the job's start to its handover. The green fill, and the line along its foot, show how far through its programme the job is.
- The diamonds are milestones: green is done, blue is on track, amber is on the critical path, and red is past its date and not complete.
- A Handover & DLP pill beside a job's name means practical completion is declared: the job is in its defects liability period, still in progress until it is completed.
- The green line down the timeline is today. Press Weeks or Months to zoom in or out, and scroll sideways to move along the timeline.
Unroll a job's programme
- Press the job's name. Its programme tasks appear underneath it, one per line, on the same timeline as the other jobs.
- A task's bar is coloured by its phase. A task past its end date and not complete pulses red; an open task on the critical path pulses amber.
- Press the name again to fold the job back to one bar.
If the job has no programme yet, the line under it says so, with a link to build one.
See what is holding up a milestone
- Press a diamond. The job unrolls and a panel opens under it listing the open job tasks linked to that milestone, each with who owns it.
- Press Start to mark a task in progress, or Done to finish it.
- Press a task's title to open it on its job's Tasks page, or open full programme to go to the job's Programme page.
- Press close to shut the panel.
If the panel says nothing is linked, either the way is clear or nobody has linked tasks to that milestone yet.
Change a programme task
- Unroll the job, then press a task's name or its bar.
- In the panel that opens, change Start, End or Status, or press Mark done. To rename the task, edit the name at the top and click away.
- Each change saves straight away. A date change moves the tasks that follow it, and the critical path is worked out again, the same as on the job's Programme page.
- Discuss in chat opens a conversation with the assistant about this task. open full programme goes to the job's Programme page. Press Escape or the cross to close the panel.
If you are not allowed to change the programme, the panel shows why when you try.
Use it on a phone
The timeline does not fit on a phone, so Portfolio is a list instead. Jobs are grouped: Milestone overdue first, then On track, then No programme yet. Each job shows its dates, how much of its programme is done and its next milestone, with the date in red when it has passed, and the Handover & DLP pill when it is in its defects liability period. Tap a job to open it.
What happens on its own
- The page keeps itself up to date. When anyone changes a job's programme, or the assistant changes it in chat, that job's bar and milestones refresh. An unrolled job also reloads when one of its tasks changes.
- Starting or finishing a task from a milestone is the same as doing it on the job's Tasks page, so the PM agent and the job's week plan see it.
- Changing a programme task here does what the same change does on the job's Programme page, including the scheduling engine and anything that follows a task being completed.
Things that surprise people
- A job in its defects liability period keeps its lane until it is completed, because it is still in progress by status. The Handover & DLP pill is how you tell it from a job still being built; the dashboard and Projects stop counting it as active.
- Portfolio shows programmes and the job tasks linked to them, nothing else. Company tasks and lead follow-ups never appear here; they are on Tasks.
- A job task shows under a milestone only while it is open and linked to that milestone. A task with no programme link is on its job's Tasks page.
- The percentage counts programme tasks with a start and an end date, milestones left out. It counts tasks, not days or dollars: a one-day task and a ten-week task count the same.
- A bar can run past the job's handover date. It stretches to take in every task on the programme, so a programme that has slipped past handover shows as a longer bar.
- A job's programme is read the first time you unroll it, so a big job can take a moment to open. After that it stays loaded while you are on the page.